Level 2 Flashcards
1
Q
What section notice did you serve at Windsor Drive?
A
Section 6(1) notice
2
Q
What are the time periods for serving notices before the works commence?
A
1 month for section 1 (Line of junction) and 6 notices (excavations)
2 month for section 3 (Party structure notice).
3
Q
You mention that there was confirmed 12 operatives at any one time?
A
The HSE must be notified via an F10 form of any project exceeding 500 person days. Total of 720 person days.
4
Q
What is a person day?
A
A person day isone persons working day. Each day a person works, they clock up one person day under CDM.