Level 1 Flashcards

1
Q

How do you undertake a progress inspection?

A

Once on site, I make contact with the site manager and walk around the property to see what progress has been made

  • Review agaisnt contractors programme
  • I record my findings with photos.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What else do you record on site when carrying out a progress meeting?

A
  • Weather
  • Number of operatives on site
  • Materials on site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why do you include a financial report in your progress report? What can it show?

A

Whether the project is within budget and if not if additional funds are required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

whos responsibility is it to report potential delays as early as possible?

A

the contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do you record when inspecting site?

A
  • Progress
  • Weather
  • Number of operatives
  • Identifying any H&S concerns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you review quality of work on site?

A
  • Checking correct / good materials are being used on site
  • Check compliance with the spec;
  • Testing required during construction phase
    • Check compliance with the Materials and Workmanship
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are quality descriptors?

A
  • Detail the standards the contractor should adhere to. For example using british standards and ensuring the manufactureres recommendations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How do you ensure quality?

A
  • Select a competent contractor;
  • Include British Standards in a specification
  • Ask for mock-ups/sample areas;
  • Check compliance with the spec;
  • Check compliance with the Materials and Workmanship
  • Warranties and guarantees.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly