Lesson 4 - Conditions of the Contract for Construction Flashcards

1
Q

Note: A201 - The Architect is not a party to the contract and is not permitted to prepare it. Only a Attorney is authorized to prepare such a document.

A

Only the owner and his leagal counsel can decide if the AIA should be used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The AIA documents were first published in 1911.

A

Supplementary Conditions are used to specify conditions that are not general.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Special Conditions are used when Supplementary conditions must be further extended.

A

h

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name the types of Bonds the Owner can require the contractor to get.

A

Performance Bond and Labor and Materials Bond.

Bonds are provided by surety companies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contractors are usually required to furnish a bid bond

A

A 310 ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Owner has to get property insurance.

A

Property Insurance is commonly known as builders risk insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Flood and Earthquake insurance must be purchased seperatley then Property Insurance.

A

Property Insurance must include riders extended coverage including theft and vandalism and malicious mischief.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An Owner may purchase loss of use insurance that protects against losses arising out of delays or other events that prevent the owner from using a project when and as intended.

A

Contractor is required to carry - Workers Compensation, Liability and personal injury insurance. Property Damage, Automobile and Contractural Liability Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What AIA COntract sumarizes the Insurance Coverage?

A

G715

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Liens are not permitted on publicaly owned property.

A

h

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Miller Act or Little Miller Acts?

A

The Miller Act is a Federal Law that will not allwo liens on Publically owned property. Instead Labor and material Payment bonds provide the necessary protection.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Force Majeure

A

Acts of God - If any days occur due to acts of god then the contractor must notify the architect whithin 21 days or the claim for time extension is waived.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Prior to submitting the first application for payment the contractor is required to submit a schedule of values for all parts of the construction work.

A

The contractor my front load the schedule. The architect reviewing teh schedule of values can prevent this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Certificate of Occupanctyi soften the same date as substansial completion.

A

The owner, the architect and the contractor must sign the certificate of substantial completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Record drawings are NOT As built drawings

A

h

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does the contractor need to submit to get final payment?

A
  1. An affidavit that all debits were satisfied.
  2. written consent of teh surey to final payment
  3. Recipts and waivers to prove that there are no obligations left on the project.
    Architect does not way in on the owners requirment of data for final payment to the contractor.
17
Q

What is required of a contractor to close out a project?

A

Its more administrative then contractural.

  1. Submission of Record Drawings.
  2. Delivery of extra stock materials, tools and parts.
  3. Removal of temp facilities.
  4. Start up testing of equipment.
  5. Final Touch up repairs and cleaning.