Lesson 3: Plan the Project Flashcards
Planning Poker(76)
- Estimates effort or relative size of development effort
- Uses a deck of cards with modified Fibonacci numbers to vote on user stories
Story points (76)
Uses a relative measure – e.g., numbers in the Fibonacci sequence – to identify the level of difficulty or complexity of
a user story or task
What are the 7 Fibonacci numbers?
0, 1, 1, 2, 3, 5, 8, 13, 21, 34, 55, 89, 144, 233… Each number, starting with the third, adheres to the prescribed formula. For example, the seventh number, 8, is preceded by 3 and 5, which add up to 8.
RACI (86)
Predictive and Agile Approach
Stands for Responsible, Accountable, Consult, and Inform. A common type of responsibility assignment matrix (RAM) that uses responsible, accountable, consult, and inform statuses to define the involvement of stakeholders in project activities.
** Remember to consider all stakeholders when creating the RACI chart and include them as appropriate.
Procurement Documents (90)
Documents used in bid and proposal activities, which include the buyer’s invitation for bid, expression of interest (EOI); invitation for negotiations; request for information (RFI); request for quotation (RFQ); request for proposal (RFP); and seller’s responses.
Contract Type: Cost plus fixed fee (CPFF)
*Reimburses
seller for all allowable costs for performing contract work; fixed-fee payment
calculated as a percentage of the initial estimated project costs.
*Fee amounts do not change unless the project scope changes.
Contract Type: Cost plus incentive fee (CPIF)
*Reimburses
seller for all allowable costs for performing contract work; predetermined
incentive fee based for achieving contract-specified performance
objectives.
*Shares costs between buyer and seller if final costs are less or greater than the original estimated costs
*Bases cost sharing on a pre-negotiated cost-sharing formula — e.g., an 80/20 split over/under goal costs
Contract Type: Cost plus award fee (CPAF)
*Reimburses seller for all legitimate costs
*Bases majority of fee on satisfying subjective performance criteria defined and incorporated into the contract
*Determines fee based on buyer’s assessment of seller performance and not subject to appeals
Decoupling
Disconnecting parts of the system to simplify and reduce the number of connect variables.
Monte Carlo Analysis
The project manager and the risk manager are using the Monte Carlo analysis to assess the possible impact of individual project risks and other sources of uncertainty on project goals. For example, if a particular risk arises, what impact will it have on the project schedule and cost? Monte Carlo provides a variety of potential outcomes and probabilities, allowing you to consider the likelihood of different scenarios (PMBOK 7th edition, page 177).
Why Cost-benfit Analysis?
To persuade an organization to select your project, the business case should be subjected to a cost-benefit analysis in order to illustrate the benefits of implementing the project by determining its anticipated financial gains and profitability. The Cost-Benefit Analysis is more comprehensive than the Net Present Value (NPV) and the Return On Investment (ROI), as it attempts to quantify both tangible and intangible costs and benefits (PMBOK 7th edition, page 175).
Context Diagram
Context diagrams are visual depictions of the product scope, displaying the business system and how it connects and interacts with other systems. It presents the inputs and outputs of the system, as well as its main players, including organizations, other business systems, end-users, etc.
Affinity Diagram (Planning Poker)
A technique that allows large numbers of ideas to be classified into groups for review and analysis.A technique that allows large numbers of ideas to be classified into groups for review and analysis.
Code of Accounts
Identifier of the WBS components.
Influence Diagram
Used in quality management decisions. A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.