Legal and Regulatory Compliance Flashcards
Level 1.
- Can you tell me the different roles a RICS member can undertake during a dilapidations?
- dilapidatons advisor
- expert witness
- ADR
- Can you explain what you did at Wigmore Lane for the dilaps assessment?
- My instruction was on behalf of the tenant
- they were looking to assign their lease over to a new tenant including their dilapidations liability.
- The new tenant had provided a terminal schedule of dilapidations
- They wanted me challenge the costs the other party had established.
- The assignee also stated they were looking for a service charge cap in respect of the landlord’s plant which they deemed to be in poor condition, this was threatening negotiations.
- I carried out a full dilaps assessment - bascially I looked at it as if doing a terminal schedule of dilapidations to ascertain the tenants liabilities, I also reviewed the lease beforehand.
- I comissioned an M and E consultant to review the plant on the floor and also to review trhe landlords plant with their permission and comment.
- If they probe deeper you can mention the landlord plant was chillers and assignee tenant surveyor had done a visual inspection only. On review of maitnenace records by my M and E consultant we were able to reduce their concerns.
*
Can you tell me what rules and srtandards govern a dilpaidations claim?
- The Civil Procedure Rules (CPR) govern how a claim should be conducted.
- The Dilapidations Protocol - drafted by RICS and the Property Litigation Association in 2000 as a guide to best practice, and revised in 2006 and 2008
What is a Calderbank offer?
- A Calderbank offer (otherwise known as a “Without Prejudice Save as to Costs”) is an offer to settle a dispute, putting the other side on notice that, if the dispute goes before any court and the outcome is less favourable to the other side compared to the Calderbank Offer being made, then the side making the offer is entitled to more of their costs being recovered.
- This is because, if the other side had accepted the offer, then they would have been better off and neither side would have had to spend money taking the matter to court.
- Arose from the Calderbank V Calderbank case 1975 between a husband and wife!
- They are useful because they are completely flexible.
- However, while they can be very persuasive in the eyes of a court when deciding whether someone has litigated unreasonably, they do not bind a court.
- Its effect is that the court is unable to refer to the offer except when dealing with the question of costs at the end of the proceedings
- A Calderbank offer provides greater flexibility than a Part 36 offer because it is not governed by strict court rules.
What is a ‘Part 36 Offer’?
- A Part 36 offer is an offer made by either the claimant or the defendant as a tactical step designed to convince the other party to settle the claim early without the matter having to go to Court
- . A Claimant who makes a sensible part 36 offer is putting their opponent under pressure to come to the negotiating table
- The name comes from the Civil Procedure Rules (CPR)
- Made at any time until judgement
- ‘Part 36′ deals with offers made on a ‘without prejudice’ basis, which means any Part 36 offers will not be seen by the Court (if the case gets that far) until after the judgment has been made and an appropriate level of compensation awarded by the Judge.
Why would you write ‘without prejudice’ in a dilaps claim corrospondance?
Marking a corrospondance “without prejudice” means that it cannot later be admitted in evidence before a court or employment tribunal without the consent of both parties concerned, should settlement negotiations subsequently break down and the dispute come before the court or tribunal.
Can you tell me what legislation affects dilapidations and briefly how?
- The Law of Property Act 1925
- section 146 - interim dilaps
- The Landlord and Tenant Act 1927 and 1954
- Section 18 - Terminal dilaps (the 1927 act)
- The Leasehold Property Repairs Act 1938
- Protects tenants in 7 year+ tenancy with more than 3 years left to run.
- The Limitation Act 1980
- statue bars damage claims after 15 years.
- The Fraud Act 2006
- The Bribery Act 2010
Can you tell me any case law regarding dilapidations?
- Proudfoot v Hart 1890
- Principle of “age character and locality’,
- Which essentially restricts the standard of repair to that appropriate for a property of that nature
- Jervis v Harris 1996
- essentially a landlord’s right to enter the property and repair on the tenant’s default, reclaiming the costs (not as per the Leashold (property) Repairs act 1938.
- Shortlands V Cargil 1995
Section 18 LTA 1921
Shortland was landlord
it was suggested that there could be no loss because the building was alleged to have a negative reversionary value.
However, the court held that there could be even greater negative value as a result of the disrepair.
Valuation A in repair (hypothetical)
and valuation B at present condition.
Proudfoot v hart 1890
Principle of ‘Good tenantable repair’
to keep a house in good tenantable repair the tenants’ obligation is to put and keep the premises in such repair as having regard to the age, character and locality of the house, would make it reasonably fit for the occupation of a tenant of the class who would be likely to take it.
E.g. compared a property in grovener square to that of one in spittalfields which in 1890 would have been a startk contrast.
The age of the house must be taken into account, because nobody could reasonably expect that a house 200 years’ old should be in the same condition of repair as a house lately buil
Tiger V Sunlife 2013
LTA 1927
Tenant Tiger had a 35 year lease with landlord sunlife
Tiger argued even if they’d left the premises in good repair, sunlife would still have had to carry out the major refub it did.
Tried to argue under section 18
Judge said diminution in value of the building would have been greater than the cost of the works
landlord won - 1.4 million
Jervis V Harris 1996
Leasehold Property (Repairs) Act 1938
Case confirmed a landlord is entitled to serve a schedule of wants of repair on the tenant and enter the property and carry out the works in default of the tenant doing so
the debt that is then claimed in respect of the cost of the works undertaken by the landlord does not have to be pursued in a manner that complies with the Leasehold Property (Repairs) Act 1938.
Shortlands V Cargil 1995
Section 18 LTA 1921
Shortland was landlord
it was suggested that there could be no loss because the building was alleged to have a negative reversionary value.
However, the court held that there could be even greater negative value as a result of the disrepair.
Valuation A in repair (hypothetical)
and valuation B at present condition.
Proudfoot v hart 1890
Principle of ‘Good tenantable repair’
to keep a house in good tenantable repair the tenants’ obligation is to put and keep the premises in such repair as having regard to the age, character and locality of the house, would make it reasonably fit for the occupation of a tenant of the class who would be likely to take it.
E.g. compared a property in grovener square to that of one in spittalfields which in 1890 would have been a startk contrast.
The age of the house must be taken into account, because nobody could reasonably expect that a house 200 years’ old should be in the same condition of repair as a house lately buil
Tiger V Sunlife 2013
LTA 1927
Tenant Tiger had a 35 year lease with landlord sunlife
Tiger argued even if they’d left the premises in good repair, sunlife would still have had to carry out the major refub it did.
Tried to argue under section 18
Judge said diminution in value of the building would have been greater than the cost of the works
landlord won - 1.4 million
Jervis V Harris 1996
Leasehold Property (Repairs) Act 1938
Case confirmed a landlord is entitled to serve a schedule of wants of repair on the tenant and enter the property and carry out the works in default of the tenant doing so
the debt that is then claimed in respect of the cost of the works undertaken by the landlord does not have to be pursued in a manner that complies with the Leasehold Property (Repairs) Act 1938.
Scottish versus BT 1994
Loss of rent (landlord and tenant 1927)
Where a landlord claims loss of rent as a head of damages at the end of the term of the lease, it is ‘an essential prerequisite that it should be demonstrated on the balance of probabilities that the carrying out of those repairs after the end of the term has prevented or will prevent the letting of the premises for that period.’
because the relevant market at the time was so depressed that it was impossible to show that the landlord would have been able to relet the premises to better advantage even if the premises had been delivered up in repair
The decision also suggested that, if a landlord were to give notice to the tenant that it was required to reinstate alterations the tenant might be able to have a reasonable period to stay at the property to enable it to complete the necessary works.
Loss of rent (landlord and tenant 1927)
Where a landlord claims loss of rent as a head of damages at the end of the term of the lease, it is ‘an essential prerequisite that it should be demonstrated on the balance of probabilities that the carrying out of those repairs after the end of the term has prevented or will prevent the letting of the premises for that period.’
because the relevant market at the time was so depressed that it was impossible to show that the landlord would have been able to relet the premises to better advantage even if the premises had been delivered up in repair
The decision also suggested that, if a landlord were to give notice to the tenant that it was required to reinstate alterations the tenant might be able to have a reasonable period to stay at the property to enable it to complete the necessary works.
When should a schedule of dilapidations be served and how long after the expiry of the lease?
- A schedule of dilapidations can be served at any time during a lease
- Up to twelve years after expiry if the lease is under seal
- Six years after expiry if the lease is under hand.
- Some leases do impose other caps on timing of service.
- There are differences in the type of schedule served depending on the timing in relation to the lease duration.
How and when can an interim schedule of dilapidations be served?
An interim schedule of dilaps can be served:
- FORMALLY
- as a notice under S146 of the Law of Property Act 1925,
- Via a right of entry clause within the lease
- INFORMALLY
- UP TO THE LAST 18 MONTHS OF TENANCY
When should a terminal schedule of dilapidations be served?
- In the last 3 years/18 months of the lease.
When should a final schedule of dilapidations be served?
- Once the lease has ended
- up to 12 years after lease end if the lease is under seal
- or six years if under hand.
What is an Interim Schedule of Dilapidations?
Interim schedules of Dilapidations are:
- served during the lease term, and can be served at any time from lease commencement.
- Whilst there is no legal bar to an interim schedule being served in the last 18 months of the lease it is more usual for a schedule at this time to be a terminal one.
- An interim schedule is not usually costed as the intention is for the party upon which it is served to rectify the breaches of covenant.
What is a Terminal Schedule of diapidations?
Terminal Schedules of Dilapidations are
- Generally served within the last 18 months of the lease
- They are intended to address all the alleged breaches of the lease, they set out the required works/ remedies.
- Typically a terminal schedule will include prices, but this may not be the case if the schedule is served a number of months before lease end
What is a Final Schedule of dilapidations
Final Schedule of Dilapidations:
- can only be served after the lease has ended.
- Under the Limitations Act 1980 an action for damages can be brought up to twelve years after the lease end if the contract was under seal (six if ‘under hand’ i.e. simply signed) though it is rare for this to be the case, as proximity of time can impact significantly on a dilapidations claim.
- Final schedules are usually in support of a claim for damages and should be priced.
What are dilapidations and what is a schedule of dilapidations?
Dilapidations
- refers to breaches of the lease covenants by either landlord or tenant, though mainly the latter, and the process of remedying the breaches.
Schedule of Dilapidations
- This is the formal listing of the alleged breaches of the contract.
- Dilapidations are not intended to profit the landlord. Any claim is merely intended to return the landlord to the same position as if the Tenant had performed their lease obligations.
What remedies are available to a landlord for dilapidations?
DURING THE COURSE OF THE LEASE:
- Specific performance (courts frown upon near end of lease say last 18 months)
- Court order complelling party to perform duties
- Apply to the Courts to end the lease under S146 of the Law of Property Act 1925 (can also use fofeiture but courts tend to favour tenant)
- erved by a landlord who wishes to commence forfeiture proceedings against a leaseholder following a breach of a lease.
- specify the breach complained of,
importantly if the breach is capable of remedy, require the leaseholder to remedy the breach, and
in any case require the leaseholder to make compensation in money for the breach.
The leaseholder is afforded a reasonable time to remedy the breach if it is capable of remedy following service of the section 146 notice.
-
Jervis v Harris Clause
- Serve an interim schedule formally under the landlord’s right of repair clause .
- If the tenant defaults on the notice enter the premises and undertake works.
- Costs may not be recoverable unless specified in the lease.
AFTER THE LEASE
- ONLY Damages recoverable- tenant cannot be asked to do the works.
Why should a terminal schedule not be served under S146 of the Law of Property Act 1925?
Terminal Schedules should not be served under S146, as the tenant cannot forfeit a lease that is about to terminate naturally
How would you go about an interim dilapidations claim?
Check the lease for
- Review the lease
- Length of the tenancy
- How long it has left to run ( to see if the Leasehold Property Repairs Act 1938 (the LPRA) will provide protection)
- Look for a Jervis V Harris Clause
- Check the landlords intentions whether they are looking to do the works (under the Jervis harris clause if present) or for the tenant to carry out the work or for the tenant to do this themselves under specific performance.
- Look for a schedule of condition
How does the Leasehold Property Repairs Act 1938 (the LPRA) protect a tenant?
- With regards interim schedules, for leases over seven years with three or more years until expiry the tenant is entitled to the relief of the Leasehold Property Repairs Act 1938 (the LPRA).
- The LPRA effectively restricts an interim schedule to matters that are essential, wind and weathertight, or so called ‘stitches in time’, where action now will prevent significant future decay and cost.
- This can be bypassed by a jervis versus harris clause in the lease.
What is a Jervis V Harris Clause what stage in the lease woud you use it?
‘Jervis and Harris clause’
- A lease clause which provides a landlord’s right to enter the property and repair on the tenant’s default, reclaiming the costs.
- This would be during the lease term (interim schedule).
- These clauses by-pass the protection of the Leasehold Property Repairs Act
- A Landlord must be careful not to interfere with the tenant’s quiet enjoyment of the property, and such clauses are usually operated as a last resort.
How would you deal with a terminal schedule of dilaps?
-
Check lease and any ancillary agreements such as LFA
- d
- Check for a schedule of condition
- Check landlord intentions (supercession Sct 18 cap LLTA 1921)
Can the tenant return to carry out repairs following expiry of the lease?
- Once a lease has expired the tenant does not have an automatic right to return to the property to undertake works and the Landlord can decide upon the nature and extent of repairs, however this may not necessarily be reflective of the Tenant’s liability
- Access may be agreed with the landlord in order carry out repairs
What is Section 18 referring to in terms of dilaps?
Section 18 of the Landlord and tenant act 1927
- places a cap on damages that can be obtained at the end of a lease to stop landlords from profiting from the claim.
- It only relates to matters of repair not reinstatement
There are two limbs:
LIMB 1 DIMINUTION OF VALUE
- The repair costs claimed must not exceed the amount the value of the reversion (the property in repair) is diminished by the tenants act.
- AKA the value lost in the property due to the tenant’s breach.
- A Diminution valuation is carried out by a specliast valuer and seeks to ascertain this value lost due to the tenant’s breach.
LIMB 2 SUPERCESSION
No repair costs shall be recovered if following the termination of the tenancy the building will be demoolished or structural alterations which would render the repairs valueless.
What club are party wall surveyors involved in ?
Pyramus and Thisbe Club
which is dedicated to the promotion of party wall education and understanding. they can be found there or on the find a surveyor service on the RICS website.
What is the Party Wall etc. Act 1996 and what does the etc mean?
Party Wall etc. Act 1996
It is enabling legilsation which provides a framework to help prevent and resolve disputes between building owner and adjoining owners in relation to building works involving party walls, boundary walls and excavations near neighbouring buildings
.
What are the 3 types of notice which can be served under the Party Wall Act
- Section 1. Line of Junction Notice
- Section 2/3. Party Structure Notice
- Section 6. Adjacent Excavation
What can you do if you need to access neighbouring land and the adjacent owner refuses access and the works are not covered by the Act and no easement exits,
- Under common law there is no right of access to neighbouring land, an owner can absolutely refuse access to their property,
- The Access to Neighbouring Land Act 1992 provides a court procedure for gaining access in certain circumstances. This takes form of an Access Order. Obtaining an Access Order through the courts can be time-consuming.
What are the possible defences for a tenant served with an interim schedule?
-
Section 146
- Claim relief of the Leasehold Property Repairs Act 1938 within 28 days of schedule service, undertaking surviving works.
- Only if their lease is 7 years + with more than 3 years left to run they may be protected under the The Leasehold (repairs) Act 1938.
- Or undertake works.
-
Jervis V Harris Clause
- Undertake works within given timescale
- Or seek Court relief against landlord entering the premises.
-
If in final 18 months of the tenancy
- Negotiate with landlord, undertaking agreed works.
- Apply to Court for relief from the schedule.
- Undertake all the work
What are the defenses for a tenant served a terminal dilaps and a final dilaps schedule?
Terminal
- Do the works
- negotiate with the landlord for settlement
Final
- negotiate with the landlord for settlement
Can you tell explain to me about the dilaps assesment you did at Wigmore Street - how was the dilapidations liability being assigned and why were you involved?
- I was acting on behalf of a tenant who was assigning their lease to a new tenant in order to respond to a schedule produced by the incoming tenant, the assignee.
- My client wanted to challenge the amounts the assignee wished to claim be paid to them to cover the outgoing tenants dilaps liability but also to investigate the service charge cap which was causing friction with the landlord.
- A tenant’s liability for dilapidations can be ‘rolled over’ on the assignment of a lease and the new tenant (the assignee) will inherit any disrepair.
- In addition to any disrepairs, the new tenant will also inherit the cost of reinstating any alterations that have been carried out during the term up to the date of assignment.
- It is up to the new tenant to negotiate a payment from the existing tenant to cover the cost of any potential dilapidations claim at the end of the term.
- Either way, a landlord should not be affected by their arrangement.
- However, in some leases the landlord has the opportunity to withhold consent to an assignment of the lease if there are serious outstanding breaches of the lease.
What is the dilapidations pre-action protocol and what is it’s objective?
The Dilapidations Pre-action Protocol
- produced by the Property Litigation Association in consultation with RICS.
- It relates to dilapidations claims for damages against tenants at the termination of a tenancy
- First published in 2002
- Requires the landlord’s surveyor to sign an endorsement confirming, amongst other things, they had followed the protocol.
- Adopted under the Civil Proceedure Rules in 2012
- The protocol applies to commercial property situated in England and Wales.
OBJECTIVE
- aim of preventing landlords exaggerating claims and to lead the way for early settlements without involvement of the courts.
- encourage the exchange of early and full information about the dispute;
What is the difference between a terminal and a final schedule of dilaps?
- terminal
- produced in last 18 months of tenancy or at the end.
What is the role of the third suveyor in party walls
To help reach an agreement if the main two survyeors cannot agree.
What does line of junction mean?
Line of junction
The term line of junction is often used in the party wall world to mean a boundary line
What is a party wall?
This is a wall that stands astride a boundary of land belonging to two or more different owners. Interestingly enough, the Act doesn’t just relate to party walls (that is why we have the etc. bit) and also it redefines different types of party walls.
What is a party fence wall
Party fence wall
The first term we will look at is the party fence wall. This is a wall that doesn’t form part of a building and stands astride the boundary line between lands of different owners. In summary, it is used to separate these lands. Typically, it is a garden wall and that is what most people would call it, but it doesn’t include a wooden fence!
What is the purpose of the dilaps protocol?
Which is the main piece of legislation surveyors are required to refer to when undertaking dilapidations?
Level 2.
What are the limitations of an asbestos management survey?
Can you tell me an example of how you complied with the approved documents during your case study project?
Regardless of size and complexity, what must all projects have as a requirement under cdm 2015.
- For all projects, commercial clients must:
- make suitable arrangements for managing their project, enabling those carrying it out to manage health and safety risks in a proportionate way. These arrangements include:
- appointing the contractors and designers to the project (including the principal designer and principal contractor on projects involving more than one contractor simultaneously) while making sure they have the skills, knowledge, experience and organisational capability
- allowing sufficient time and resources for each stage of the project
- making sure that any principal designer and principal contractor appointed carry out their duties in managing the project
- making sure suitable welfare facilities are provided for the duration of the construction work
- maintain and review the management arrangements for the duration of the project
- provide pre-construction information to every designer and contractor either bidding for the work or already appointed to the project
- ensure that the principal contractor or contractor (for single contractor projects) prepares a construction phase plan before that phase begins
- ensure that the principal designer prepares a health and safety file for the project and that it is revised as necessary and made available to anyone who needs it for subsequent work at the site
Level 3.
When are you unable to serve an interim schedule of the dilapidations?
At the end of the tenancy or when it has expired, courts would also take a dim view in the final 18 months of the tenancy
What clauses would you typically consider when undertaking a schedule of dilapidations?