LEED Process Flashcards
A team in a goal setting-workshop has selected to pursue LEED Gold, identified credits to pursue and assigned responsible parties to each credit and prerequisite. After evaluating possible energy strategies what does the team need to document for IP Credit Integrative Process?
A. The credit calculations for each credit
B. The aggregate costs of the meetings
C. How the analysis informed the design decisions in the OPR and BOD
D. The preliminary project schedule
C. How the analysis informed the design decisions in the OPR and BOD
The credit documentation requires describing how the analysis informed the design decisions in the project’s OPR and BOD.
Which project strategy would earn an exemplary performance point under IN Credit Innovation Option 3 Additional Strategies?
A. Achieve EQ Credit Interior Lighting Option 1 Lighting Control and EQ Credit Interior Lighting Option 2 Lighting Quality
B. Provide views for 90% of all regularly occupied areas
C. Demonstrate spatial daylight autonomy of at least 90% is achieved for regularly occupied floor areas
D. Agree to purchase RECs for 10 years
B. Provide views for 90% of all regularly occupied areas
EQ Credit Quality Views can earn exemplary performance by providing views for 90% of all regularly occupied areas.
A LEED reviewer has sent a project team technical advice on one of the design credits that was submitted in a split review. What does the project team need to do?
A. Respond to the technical advice the LEED reviewer sent
B. Nothing, it is up to the project team if they want to take the advice of the reviewer
C. Document a narrative for the technical advice and submit it during any appeals process
D. Update the narrative of the credit and resubmit it for another design review
A. Respond to the technical advice the LEED reviewer sent
When a LEED reviewer responds to a credit/prerequisite the review will contain comments and technical advice. Technical advice includes things that need to be revised and updated for the credit/prerequisite to be earned. An example might be ‘Revise the building operating plan to include all design setpoints for all HVAC equipment throughout the building.’ or ‘Provide a revised preventive maintenance plan that includes…’.
Which statement is true about Credit Interpretation Requests (CIRs)?
A. CIRs cannot be submitted in regard to the LEED Accredited Professional credit.
B. Product vendors can access all CIRs to meet any updated credit requirements.
C. CIRs can only be submitted during the design phase of a project.
D. CIRs can be submitted for prerequisites.
D. CIRs can be submitted for prerequisites.
CIRs can be submitted for any prerequisite or credit for the project’s rating system.
A project was registered in January of 2013. In April 2013 USGBC published Addenda for a credit the project team is pursuing. What statements are true regarding this project? (Choose 2)
A. The project team must follow any addenda published in April, 2013
B. The project team can choose to follow any addenda published prior to January, 2013
C. The project team can choose to follow any addenda published after April, 2013
D. The project team must follow any addenda published prior to January, 2013
C. The project team can choose to follow any addenda published after April, 2013
D. The project team must follow any addenda published prior to January, 2013
A LEED AP in a goal setting workshop is working on their first LEED BD+C: Schools project. What prerequisites would be applicable to the project and need to be assigned to team members?
A. SS Prerequisite Environmental Site Assessment and EQ Prerequisite Minimum Acoustic Performance
B. MR Prerequisite PBT Source Reduction - Mercury and SS Prerequisite Environmental Site Assessment
C. IP Prerequisite Integrative Project Planning and Design and MR Prerequisite PBT Source Reduction
D. EQ Prerequisite Minimum Acoustic Performance and IP Prerequisite Integrative Project Planning and Design
This is the answer — A. SS Prerequisite Environmental Site Assessment and EQ Prerequisite Minimum Acoustic Performance
The following credits / prerequisites are specific to Healthcare only. It is important to know which credits/prerequisites are specific to the different rating systems
Healthcare:
IP Prerequisite Integrative Project Planning and Design
SS Credit Places of Respite
SS Credit Direct Exterior Access
MR Prerequisite PBT Source Reduction - Mercury
MR Credit PBT Source Reduction - Mercury
MR Credit PBT Source Reduction - Lead, Cadmium, and Copper
MR Credit Furniture and Medical Furnishings
MR Credit Design for Flexibility
Schools:
SS Prerequisite Environmental Site Assessment
SS Credit Site Master Plan
SS Credit Joint Use of Facilities
EQ Prerequisite Minimum Acoustic Performance
B. MR Prerequisite PBT Source Reduction - Mercury and SS Prerequisite Environmental Site Assessment
MR Prerequisite PBT Source Reduction - Mercury is for LEED BD+C: Healthcare.
C. IP Prerequisite Integrative Project Planning and Design and MR Prerequisite PBT Source Reduction
Both of these are for LEED BD+C: Healtcare.
D. EQ Prerequisite Minimum Acoustic Performance and IP Prerequisite Integrative Project Planning and Design
IP Prerequisite Integrative Project Planning and Design is for LEED BD+C: Healthcare.
A project team member has excluded a section of land in order to meet the requirements of one of the LEED credits. Which statement is true about this action?
A. This action is not allowed.
B. This action is allowed if the gross floor area of the LEED project building is less than 2% of the gross land area within the LEED project boundary.
C. This action is only allowed if a project narrative is written to explain the exclusion.
D. Certain sections of land can be excluded from the site boundary if a responsible party submits a licensed professional exemption form.
A. This action is not allowed.
Land cannot be excluded for the purposes of complying with a credit/prerequisite. This is known as gerrymandering.
If a project boundary is not obvious because of ownership by multiple entities, which action should the project team take?
A. Submit a CIR
B. Use a boundary that best serves the project
C. Ask the project owner which boundary to use
D. Review the minimum program requirements
D. Review the minimum program requirements
This is the first place to look for suggestions.
A LEED BD+C project will be constructed and operated on a permanent location on existing land, and will be a minimum of 1,000 SF (93 m2). What else must the project do to meet the minimum program requirements?
A. The project team must perform a simple energy box model
B. The project must have at least one LEED AP on staff
C. The owner must hire a CxA that has experience on at least two other LEED projects
D. The project boundary must include all contiguous land that is associated with the project and supports its typical operation
D. The project boundary must include all contiguous land that is associated with the project and supports its typical operation
This is the 3rd MPR the project would need to meet.
An office complex near a lake is being designed. The project will be built on a prime tract of undeveloped real-estate 40 ft. (12 meters) from the lake. The project will be located 1/8 mile (200 meters) from 3 public bus lines.
Which credit would NOT be achievable for the project?
A. SS Credit Rainwater Management
B. SS Credit Site Development-Protect or Restore Habitat
C. LT Credit Sensitive Land Protection
D. LT Credit Access to Quality Transit
C. LT Credit Sensitive Land Protection
A project team wishes to get a Credit Interpretation Request on a credit and prerequisite that are unrelated. Which action will assist with this process?
A. Submit only one CIR for the prerequisite
B. Submit one CIR covering both the credit and prerequisite
C. Submit two CIRs: one for the credit and one for the prerequisite
D. Submit only one CIR for the credit
C. Submit two CIRs: one for the credit and one for the prerequisite
Inquiries must request guidance on just one credit or prerequisite (unless there is technical justification to do otherwise) and generally contain one concise question or a set of related questions.
Projects spend money on CIRs for prerequisites for the same reason as for credits - to find out if a particular solution qualifies the project for meeting the requirements. The project may meet the requirements of the prerequisite but sometimes submitting a CIR is the only way to find out.
The project team for an office building is considering a composting program. Which statement is true regarding the IN Credit Innovation for a composting program?
A. Composting 100% of a project’s organic waste can earn the project exemplary performance.
B. LEED would reject IN Credit Innovation submission for a composting program unless it was a Regional Priority.
C. A LEED AP would be required to design a composting-management plan in order to meet the IN credit requirements.
D. If Project ABC earns IN Credit Innovation for implementing a composting program, then Project XYZ will also earn the credit.
E. IN Credit Innovation can only be earned if all occupants of the building are allowed to participate in the program.
E. IN Credit Innovation can only be earned if all occupants of the building are allowed to participate in the program.
The three basic criteria for achieving an IN credit for a category not found in the LEED rating system are as folows:
Quantitative. This means the concept must have measurable/quantifiable environmental benefits. Establish a baseline and compare it with the final outcome to determine the improvement. How much environmental benefit did the strategy achieve?
Comprehensive. The process or specification must be comprehensive. For example, if a new material could be used in every floor of a building, the project team can’t use it in just one floor. A process that only addresses a part of the project isn’t considered comprehensive and does not meet the credit requirements.
Transferrable. The concept must be able to be used on other projects by other project teams. It can’t be a concept that only applies to a unique aspect of one project.
The IN point for a composting program would only be allowed if all building occupants would have access to the program. For example, a project team can’t say that they are limiting a program to the occupants on floors 1-5 and that occupants on floors 6-10 can’t participate because there isn’t enough space for all the compost.
Which action is an example of an overlapping benefit that a project team might find during ongoing discovery while iteratively testing alternatives and refining an analysis?
A. Deciding to increase ventilation by 30%
B. Using the waste heat from a mechanical system to heat hot water
C. Selecting one paint over another for aesthetic reasons
D. Removing an underfloor air-distribution system due to cost
B. Using the waste heat from a mechanical system to heat hot water
This is an example of looking for new opportunities in the design that support the project goals.
Which special considerations would be part of the LEED project scope? (choose 2)
A. A shared facility that may be used by the project occupants
B. Underground parking
C. An off-site amenity
D. Daylight modeling
A. A shared facility that may be used by the project occupants
C. An off-site amenity
Which elements are not covered under the LEED BD+C: Core and Shell rating system? (choose 2)
A. Structure
B. HVAC system
C. Envelope
D. Tenant fit-out
E. Furniture, furnishings, and equipment (FF&E)
D. Tenant fit-out
Tenant fit-outs are part of the LEED ID+C.
E. Furniture, furnishings, and equipment (FF&E)
FF&E are part of the LEED ID+C rating systems. Furniture is also addressed in LEED BD+C.
The owner of a space has had a lot of turnover in the project team, resulting in delays in LEED documentation. How long can the project team wait to submit the construction phase review?
A. No later than 18 months after any new version of LEED is released
B. No later than two years after the project is substantially completed
C. No later than two years after signing the lease agreement
D. No later than 18 months after project registration
B. No later than two years after the project is substantially completed
Deadline for submitting for review
For LEED BD+C and LEED ID+C rating systems, you will need to submit for your construction phase review (preliminary standard review or preliminary construction review) no later than two years after your project is substantially completed (the date on which your building receives a certificate of occupancy or similar official indication that it is fit and ready for use).
A national park located in MLO lighting zone 2 has walking paths around a lake, a 150-car parking lot, a national flag in front of the visitors center, and a small amphitheater for giving presentations. The road leading to the park has government mandated lighting. What exterior lighting would be exempt from SS Credit Light Pollution Reduction?
A. National flag, the amphitheater, and the roadway
B. Walking paths, landscape lighting, and parking lot
C. Parking lot, roadway, and walking paths
D. Roadway, national flag, and parking lot
A. National flag, the amphitheater, and the roadway
There are exemptions from uplight and light trespass requirements. Check the rating system requirements for the complete list of exempt lighting.