lecture 5: ancillary services Flashcards

1
Q

regulating power & energy: 3 types

A

primary, secondary and tertiary control reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

primary control reserve

A

Frequency Containment Reserve FCR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

FCR purpose, capacity, response time, frequency deviation corrected

A

stabilization of the frequency, +-3000 MW in continental ENTSO-E, delivered after at most 30s, until at most 15 min, activated for deviations of > +-200 mHz

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

frequency of the ENTSO-E grid, deviation max

A

50 Hz, 200 mHz

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

secondary control reserve

A

automatic Frequence Restoration Reserve aFRR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

aFRR purpose, response time

A

release the FCR, 15 min if required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

tertiary control reserve

A

manual Frequency Restoration Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cause of uncertainty in forecasting electricity supply

A

Wind (cut-out wind speed can be reached), solar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Power wind turbine = f(wind speed)

A

Speed^3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Other ancillary services

A

Reactive power (phase shift between U and I, cannot be transported over long distance: only local), losses, black start (islanded operation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Relation between losses and reactive power

A

High voltage -> low losses high reactive power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

FCR cooperation

A

Core share: FCR that must be physically delivered in each country.
Total FCR contribution = core share + net imports. Exports limits exist (physical constraints).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Market structure for control reserves

A

Auctions with merit order for all bids.
FRR: towards a unique market in entsoe

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reactive power and voltage control

A

Local, no real global market

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Balance group

A

Aggregation of producers, consumers, traders that can exchange on the day ahead market to other balance group. Aggregation is virtual (no physical relevance).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Control zone

A

Set of balance groups that are under control of the TSO

17
Q

Balance energy price mechanism

A

Punitive price: Energy in excess to schedule is paid less than P, energy in default must be purchased at more than P. P = reserve or spot market (depending if control reserve is activated)

18
Q

Post scheduling

A

The origins of unbalances are determined ex post. Day-after trading: short notice direct trade bypassing the TSO, balance corrected ex post.