Lecture 3: Scheduling Flashcards

1
Q

Why is it important to plan?

A
  • Basis of time management
  • Can be used as a communication tool - forecasting, controlling, monitoring and benchmarking
  • Allows for the considered adjustment of scarce resources
  • Contractual obligation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain the project planning order.

A
  1. The project charter
  2. Scope management
  3. Method Statements
  4. Work Breakdown Structure
  5. Planning of time, cost, labour resources using a suitable planning tool
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a project charter?

A

A high level statement of what is to be done and the boundaries of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is scope management?

A

The translation of the high level statement into detailed documentation which becomes the project brief. Typically this will be in the form of drawings, specification and a bill of quantities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are method statements?

A

Build-method outlines created which outline how the product will be assembled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Explain work breakdown structure.

A

Subdividing the scope of the work of a project into activites/ manageable packages for cost estimation and scheduling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is level 0 of a WBS and what does it produce?

A

Level 0 is the project, and in this level the master programme is produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is level 1 of a WBS and what does it produce?

A

Level 1 is the location or the subcontractors, and in this level a tender or contract programme is produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is level 2 of a WBS and what does it produce?

A

Level 2 is the activites/ stages of the job, and section, stage or short term programme is produced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does project control enable a project team to do?

A

Any project team should be able to ask at any time:

  • Where are we?
  • How did we get there?
  • Where do we want to be and how do we get there?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Describe the essence of project management planning.

A
  • Work breakdown into tasks - identify what needs to be done
  • Estimate the duration of each identified task
  • Optimise the sequence of tasks
  • Reconcile the analysis with the actual availability of resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the requirements of an effective planning system?

A
  • Sensible and realistic
  • Content must be relevant
  • Must be interrogative and interactive
  • Must be flexible
  • System should be dynamic
  • Must communicate information clearly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

List planning tools.

A
  • calendars
  • histograms
  • gantt bar charts
  • network analysis (critical path method or precedence diagrams)
  • line of balance - vertical production planning
  • last planner
  • theory of constraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the critical path?

A

The series of activites that have zero float.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is activity float?

A

A measure of an activities flexibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is free float?

A

Float an individual activity can use up without effecting the early start of the next activity.

17
Q

What is total float?

A

The float shared with other activities in a group (arm).

18
Q

What are the steps of the precedence diagram method (PDM)?

A
  • Estimate the duration of each activity
  • Initial take-off should be unconstrained
  • Establish relationships between activities
19
Q

Describe Finish to Start (FS) activity takeoff.

A

Activity B cannot start until Activity A is finished.

20
Q

Describe Start to Start (SS) activity takeoff.

A

Activity B cannot start until Activity A has started.

21
Q

Describe Finish to Finish (FF) activity takeoff.

A

Activity B cannot finish until Activity A is finished.

22
Q
Define:
Early start (ES)
Early finish (EF)
Late start (LS)
Late finish (LF)
A

ES: earliest time an activity can start
EF: earliest time an activity can finish
LS: latest time an activity can start without project delay
LF: latest time an activity can finish without project delay

23
Q

Computations:

A
EF = ES + Duration
LS = LF - Duration
Total Float TF = LF - ES - Duration
Start Float SF = LS - ES
Finish Float FNF = LF - EF
24
Q

What are some short comings of PDM?

A
  • All goals are based on estimates, which contain uncertainties
  • Estimates of activity times generally include a large safety margin
  • Human nature for many of us means activities are left to the last possible minute
  • ‘Parkinson’s Law’ may prevail: an activity will expand to fill the time available
  • The way that progress is measured is in error - by the time the PM is notified of a problem it is already to late to prevent it.