Lecture 10: Project Mgmt Flashcards
1
Q
project def
A
new product/service/event, difficult to plan/ control, constraints
2
Q
project mgmt def
A
planning, scheduling, controlling a project
3
Q
project mgmt methods
A
Gantt chart, CPM
4
Q
Data needed for project mgmt
A
list of activities, relation between activities, duration estimates
5
Q
CPM method
A
activities are arcs, nodes represent events
6
Q
immediate predecessor
A
activity A must be completed before B can start
7
Q
Formulas in CPM
A
ES = max(EF of all predecessors) or 0
EF = ES + t
LF = min(LS of all successors) or T
LS = LF -t
S = LS - ES = LF-EF
T = max(EF)
8
Q
Steps for CPM
A
1) draw precedence graph of the project
2) Find EF/ES
3) Go backwards to find LF/LS
5) Find the critical path
9