Lecture 10: Project Mgmt Flashcards

1
Q

project def

A

new product/service/event, difficult to plan/ control, constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

project mgmt def

A

planning, scheduling, controlling a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

project mgmt methods

A

Gantt chart, CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Data needed for project mgmt

A

list of activities, relation between activities, duration estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CPM method

A

activities are arcs, nodes represent events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

immediate predecessor

A

activity A must be completed before B can start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Formulas in CPM

A

ES = max(EF of all predecessors) or 0
EF = ES + t
LF = min(LS of all successors) or T
LS = LF -t
S = LS - ES = LF-EF
T = max(EF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Steps for CPM

A

1) draw precedence graph of the project
2) Find EF/ES
3) Go backwards to find LF/LS
5) Find the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly