lean amine Flashcards
1
Q
Description of Incident:
A
Event Timeline:
1- Feed from GTU contains high concentration of hydrocarbon C3-C4.
2- Activated carbon filter malfunction S-2105.
3- Foaming in top of absorber C-2101.
4- Level increase in V-2007 due to lean amine carryover with foam.
5- Lean amine concentration drops.
2
Q
Impact of The Incident:
A
- Moisture was carried over to K-2001 causing low delivery which led to the anti-surge valve to open.
- Amine concentration drop.
3
Q
A