LBYIE3F Quiz 1 Flashcards

1
Q

BAC (Budgeted At Completion)

A

Add all the task values above the Gantt chart components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV (Planned Value)

A

Add everything on the left side of the red line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC (Actual Cost)

A

Add all actual cost values

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

EV (Earned Value)

A

ROP x PV; then add everything

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SV (Schedule Variance)

A

EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SPI (Schedule Performance Index)

A

(EV / PV) x 100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CV (Cost Variance)

A

EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI (Cost Performance Index)

A

(EV / AC) x 100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

TCPI (To-Complete Performance Index)

A

( (BAC - EV) / (BAC - AC) ) x 100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC (Estimated Cost at Completion)

A

AC + ( (BAC-EV) / SPI )

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC (Variance at Completion)

A

BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

ETC (Estimated Time to Completion)

A

Total Project Duration / SPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SPI Conditions:

A

SPI > 100%; Project is ahead of schedule

SPI < 100%; Project is behind schedule

SPI = 100%; Project is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CPI Conditions:

A

CPI > 100%; Project is under budget

CPI < 100%; Project is over budget

CPI = 100%; Planned cost = actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly