last 50 Flashcards
- Using Figure 9a what is the budgeted unit
work hours in work hours per unit for the
column forms?
A. 0.045
B. 0.171
C. 0.241
D. 5.838
b see figure sla
428/2499
- Using Figure 9a what is the weekly unit
work hours in work hours per unit for the
column forms?
A. 0.007
B. 0.195
C. 4.919
D. 5.118
b 17/87=.195
Using the information provided in Figure
9a what is the to date unit work hours in
work hours per unit for the column forms?
A. 0.011
B. 0.241
C. 3.821
D. 4.148
a 27/112
. Using the information provided in Figure
9a what are the total earned work hours
for the column forms?
A. 19
B. 27
C. 465
D. 2,387
112.x.171=19
Using the information provided in Figure
9a what is the total projected work hours
at completion for the column forms?
A. 27
B. 104
C. 602
D. 2,472
c 2499*.241=602
Using the information provided in Figure
9a what is the projected gain/loss in work
hours for the column forms?
A. (174)
B. 325
C. 1,897
D. 2,396
a 428-602
Using the information provided in Figure
9b what is the budgeted unit cost in dollars
per unit for the concrete footings?
A. 0.047
B. 21.45
C. 137.25
D. 256.00
b 5490/256
Using the information provided in Figure
9b what is the week labor unit cost in
dollars per unit for the concrete footings?
A. 0.70
B. 1.43
C. 3.14
D. 14.60
365/25 d
Using the information provided in Figure
9b what is the to date unit cost in dollars
per unit for the concrete footings?
A. 0.32
B. 3.14
C. 20.13
D. 5,125.00
c 805/40=20.13
Using the information provided in Figure
9b what is the total projected cost at
completion for the concrete footings?
A. 81.41
B. 803.84
C. 5,150.72
D. 10,615.00
256x20.12=c
Using the information provided in Figure 9c
what is the current projection for the
quantities of piles in vertical linear feet
(VLF)?
A. 680
B. 5,300
C. 5,980
D. 6,700
c 6700-720=5980
. Which statement is true about the critical
path?
A. Is the shortest string of activities
through the schedule
B. Is the longest string of activities through
the schedule
C. Has zero total float but possibly some
free float in the activities
D. Includes all activities that are
impossible to compress their duration
any further
b
- How is free float defined?
A. The amount of slack in a node
B. The amount of slack between activities
C. The amount of slack within a series of
activities
D. The amount of slack accumulated
throughout the logic network
b
Which types of activities are considered
first when compressing the length of a
project?
A. Zero float and least cost to compress
B. Zero float and highest cost to compress
C. Highest floats and least cost to
compress
D. Highest floats and highest cost to
compress
a
How is the term fast tracking defined in
construction?
A. Planning and scheduling the design
B. Overlapping execution of the
construction activities
C. Finalizing the design and procurement
before construction begins
D. Overlapping execution of the design,
procurement, and construction
d
What is the name of the term for shifting
the activities within their available free
floats to produce a uniform workforce and
reduce the maximum resource usage
requirements?
A. Crashing
B. Crew utilization
C. Resource leveling
D. Time-scaled networking
c
- What is the best source for developing the
list of activities for the logic network and
schedule?
A. General requirements
B. Technical specifications
C. Financial reports and balance sheets
D. Estimate and earned work hour report
b
How is total float defined?
A. The amount of slack in a node
B. The amount of slack within an activity
C. How much a series of activities can be
delayed without delaying a project
D. The amount of slack accumulated
throughout the logic network
c
. Using the information provided in Figure
10, what is the total number of days to
complete this sequence of activities?
A. 13
B. 14
C. 18
D. 31
b see figure s2
Using the information provided in Figure
10, what are the critical activities for this
logic network?
A. B, G
B. A, C, F
C. A, D, E, G
D. A, C, F, G
d s2