L7 - Contract Law- Discharge, Breach of Contract Flashcards
What is the Discharging of a Contract?
- The obligations of a contract come to an end.
- All duties which arose under the contract are terminated.
- The parties are no longer bound by law.
What are the 4 main ways to discharge a contract?
- agreement
- Breach of Contract
- Performance
- Frustration
What are the two types of Agreement as a way to discharge a contract?
can be done two ways:
- bilateral agreement
- unilateral agreement
What a bilateral agreement?
- Neither party has completed all obligations.
- They agree to release each other from the agreement.
- Each receive a benefit from the release
What is a Unilateral Agreement?
One party has completed all obligations but the other one wishes to be released before completion.
- (a) Consideration for the release is needed –> pay off the rest of the contract OR
- (b) an agreement by deed is made.
(a) When there is consideration the agreement is an ACCORD and the consideration is called SATISFACTION. The arrangement is referred to as an accord and satisfaction.
What is Performance as a way to Discharge a contract?
General Rule
- Each party does precisely what they promised to do.
- The contract ends because all obligations have been performed in full.
- It must not be less than agreed.
- If a party does not totally complete their side cannot sue on it.
What is the Case of Performance as a way to discharge a contract?
Cutter v Powell (1795)
What is the Case of Cutter v Powell (1795)?
0 Cutter agreed he would sail with Powell from Kingston, Jamaica to Liverpool, England. The contractual note read as follows.
- “Ten days after the ship Governor Parry, myself master, arrives at Liverpool, I promise to pay to Mr. T. Cutter the sum of thirty guineas, provided he proceeds, continues and does his duty as second mate in the said ship from hence to the port of Liverpool. Kingston, July 31st, 1793.”
- Cutter died after seven weeks and Powell didn’t pay the widow any money at all.
- His wife sued for part payment.
What is the Issue of Cutter v Powell (1795)?
Issue:
Performance of contract
What is the Ruling of Cutter v Powell (1795)?
Ruling:
The contract required entire performance and payment was agreed on completion of the voyage.
Harsh? Unjust?
What are the 4 exception to Performance as a way to Discharge a Contract?
Due to the harshness of ‘Cutter v Powell’, four exceptions are allowed.
- Substantial Performance.
- Divisible Contracts
- Acceptance of Partial Performance
- Prevention of Complete Performance
What are the 5 cases of exception to Performance as a way to Discharge a Contract?
- Hoenig v Isaacs (1952)
- Bolton v Mahadeva (1972)
- Ritchie v Atkinson (1808)
- Sumpter v Hedges (1898)
- Planche v Colburn (1831)
What was the Case of Hoenig v Isaacs (1952)?
- Mr Hoenig was meant to decorate and furnish Mr Isaac’s flat for £750.
- When the work was done, there were problems with a bookcase and wardrobe, which would cost £55 to fix.
- Mr Isaac refused to pay the £350 outstanding.
What was the Issue of Hoenig v Isaacs (1952)?
Issue:
Substantial Performance of contract?
What was the Ruling of Hoenig v Isaacs (1952)?
Ruling:
The contract was substantially performed.
The claimant was entitled to the contract price less the £55.
What was the Case of Bolton v Mahadeva (1972)?
- Mr Bolton installed central heating for £560 in Mr Mahadeva’s house.
- It was too cold, the heat came unevenly and it gave off fumes.
- Bolton refused to correct it, which would cost £174. Mahadeva refused to pay any money at all. Bolton sued.
What was the Issue of Bolton v Mahadeva (1972)?
Issue:
Substantial Performance of contract?
What was the Ruling of Bolton v Mahadeva (1972)?
Ruling:
Held that Bolton was entitled to nothing because there had been no substantial performance at all.
What was the Case of Ritchie v Atkinson (1808)?
- By contract the claimant agreed to carry a cargo of specified quantity of hemp and iron.
- The price agreed was £5 per ton for the hemp and 5 shillings per ton of iron. The claimant only carried part of the agreed quantity.
- The defendant argued the contract had not been fully performed and therefore no payment was due.
What was the Issue of Ritchie v Atkinson (1808)?
Issue:
Performance of divisible contract?
What was the Ruling of Ritchie v Atkinson (1808)?
Ruling:
- Held. The contract could be divided into separate parts as the parties had agreed a price per ton.
- The claimant was thus entitled to payment for the amount carried although the defendant was entitled to damages for non performance in relation to the amount not carried.
What was the Case of Sumpter v Hedges (1898)?
- Mr Sumpter was a builder. He had a contract to build two houses and stables for Mr Hedges for £560.
- He did work valued at £333 and said he had to stop because he had no more money.
- Hedges finished the building, using materials which Sumpter had left behind.
- Sumpter sued for the outstanding money.
What was the Issue of Sumpter v Hedges (1898)?
Issue:
Performance of partial contract?
What was the Ruling of Sumpter v Hedges (1898)?
Ruling:
- Bruce J found that Mr Sumpter had abandoned the contract.
- He could obtain money for the value of the materials but nothing for the work.
The party accepting partial performance must have a genuine choice whether to accept or reject the partial completion of the contract.
What was the Case of Planche v Colburn (1831)?
- The claimant agreed to write a book on costume and armour .
- The agreed contract price was £100 to be payable on completion. The claimant commenced writing and had completed a great deal of it when the defendant cancelled the series.
- The defendant refused to pay the claimant despite his undertaking and the fact that the claimant was still willing to complete.
- The claimant brought an action to enforce payment.
What was the Issue of Planche v Colburn (1831)?
Issue:
Prevention of Complete Performance?
What was the Ruling of Planche v Colburn (1831)?
Ruling:
Held: The claimant was entitled to recover £50 because the defendant had prevented the performance.
What is a Breach as a way to discharge a contract?
If one of the parties breaks or has indicated they intend to break one or more of the contract terms.
- Serious Breach – Terminated
- Insignificant Breach – Warranty (damages), but innocent party must still uphold their side of the bargain.
What is a serious Breach?
- Breach of terms – when the contract is due and one party fails to carry it out.
- Repudiation (anticipatory) – when a party expressly informs the other that they do not intend to carry out the contract.
What is a Repudiation or Anticipatory Breach?
- the innocent party has the option to treat their obligations under the contract as being immediately at an end.
- They can also recover damages for the loss of benefit they would have had if the contract was performed.
- the innocent party has no obligation to sue straight away. They have a choice.
- They could wait to see if the contract comes good.
- Contract could be ‘frustrated’ in the meantime.
What were the 3 Cases of an Anticipatory Breach as a way to discharge a contract?
- Hochster v De La Tour (1853)
- Vitol SA v Norelf Ltd (1996)
- Avery v Bowden (1856)
What was the Case of Hochster v De La Tour (1853)?
- In April, De La Tour agreed to employ Hochster as his courier for three months from 1 June 1852, to go on a trip around the European continent.
- On 11 May, De La Tour wrote to say that Hochster was no longer needed.
- On 22 May, Hochster sued.
- De La Tour argued that Hochster was still under an obligation to stay ready and willing to perform till the day when performance was due, and therefore could commence no action before.
What was the Issue of Hochster v De La Tour (1853)?
Issue:
Anticipatory Breach?
What was the Ruling of Hochster v De La Tour (1853)?
Ruling:
Held: The claimant did not have to wait until the contract was actually breached.
As soon as they were aware they could bring an action.
What was the Case of Vitol SA v Norelf Ltd (1996)?
- Vitol ordered goods from Norelf to be loaded and delivered by ship.
- Whilst at sea V sent a telex rejecting goods. A breach of contract.
- On receipt of telex, N didn’t communicate with V, nor send the usual bill of lading.
- N then sold the goods to a 3rd party and sued V for breach of contract.
What was the Issue of Vitol SA v Norelf Ltd (1996)?
Issue:
Anticipatory Breach?
What was the Ruling of Vitol SA v Norelf Ltd (1996)?
Ruling:
Held: The claimant did not have to communicate their acceptance of the breach if their conduct shows it is at an end. By not sending the bill of lading showed they were treating it as finished.