High early strength concrete is known as type _
III
The first pass made towards levelling the surface of a newly poured concrete slab is called _
Screeding
The on-site test to test for a concrete mix’s wetness and workability is called a _ test
Slump
T/F When placing concrete using a crane and bucket, formwork is NOT required
False
In order to ensure that concrete reaches its design strength, it needs to be kept moist for AT LEAST _ days
7
Given concrete’s zero design strength in terms of tension and shear, _ are required to be installed near the points of support to handle the shear stresses
Stirrups
In casting a site cast concrete wall, _ _ penetrate through the formwork and prevent the forms from bursting outwards or collapsing inwards
Form ties
T/F A limitation of one-way structural slab is that the columns must be placed in square or near-square configurations
False
A one way floor system that seeks to reduce floor-to-floor heights is called a _ slab
Banded
As a method for strengthening the slab to column connection, the waffle slab features _, which form the same purpose as drop panels in flat slabs
Heads
T/F Arguably the best solution for minimising the floor-to-floor height of a high-rise building is a two-way flat plate
True
Lift-slab construction uses which type of site cast concrete floor framing system (solid, banded, ribbed, flat, flat plate, waffle slab, none)
Flat plate
L-shaped and inverted tee girders feature _, which support slabs or beams
Ledger
In order to avoid problematic concrete-to-concrete connections, _ _ are installed to separate pre-cast framing elements
Bearing pads
T/F A concrete topping creates an important diaphragm within pre-cast framing systems that works towards resisting lateral forces
True