L4 - Time-Impact on schedules Flashcards
1
Q
Time Impact analysis
A
Unplanned delays.
Delays beyond the GC’s control.
Construction law.
Time impact analysis.
2
Q
Non-excusable delays
A
Normal weather. Inadequate workforce/supervision/equipment. Untimely material procurement. Failure to coordinate subs. Shortage of capital. Foreseeable labor problems.
3
Q
Non-compensable delays
A
Acts of God.
Strikes/labor unrest.
Unusually severe weather.
4
Q
Excusable delays
A
No liquidated damages.
Could be compensable or non-compensable.
5
Q
Compensable
A
By time/money. Changes. Shop drawing review. Site availability. Owner-furnished material. Disruption.