L2 - CPM Building Blocks Flashcards

1
Q

Essential ingredients

A

Activities
Durations
Logic relationships
Constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of Logic and relationship Lag

A
F to S
F to S with pos. lag
F to S with neg. lag
F to F
F to F with lag
S to S
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When developing logical relationships consider:

A

Physical limitations: foundations>walls>roof.
Contractual requirements.
Availability of resources or other: limited # of crews available, tight schedule requires concurrent work, most profitable work schedule first.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Constraints

A

Imposed restrictions used to reflect project requirements that cannot be built into the logic.
Aid in building a schedule that more accurately reflects the real world aspects of your project.
Provide added control in the schedule.
Can be abused.
Too many constraints cloud the impact of certain events.
Unnecessary constraints defeat the purpose/value of CPM software.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Types of constraints

A

Date
Duration
Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Typical constraints

A

Finish no later than:
-Indicates the date by which an activity must finish.
-Affects late dates.
-Used during backward pass.
-Affects the late dates of predecessor activities.
Start on:
-Imposes start-no-earlier-than and start-no-later-than constraint on same activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPM theory - forward and backward pass

A

In: activities, relationships, constraints.
CPM ALGORITHM
Out: Early/Late S and F dates, critical path, float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPM theory - definitions

A

Early S/F: The earliest an activity can possibly S/F as dictated by all related activities.
Late S/F: The latest an activity must S/F so as not to delay the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

CPM theory - method

A

Forward pass: calculates early S/F dates
Backward pass: calculates late S/F dates
Total Float: number of days that an activity can be delayed without delaying the end date of the project.
TF= LF-EF
Free Float: amount of time an activity can slip without impacting the early start of successor activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Critical Path

A

The longest continuous path of project activities that controls the completion of the project.
On a new schedule the critical path has zero total float.
Delayed project, total float is -.
CPM schedule allows forecasting the effect of changes.
One day of delay to an activity on the critical path causes one day of delay to the project completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

More basic definitions

A

Milestone: Activity with zero duration.
Constraint: Overrides the calculated date.
Calendar: User defined work and non-work periods.
Hammock: Summary level activities.
Activity code: used to group and organize activities.
Resource and cost loading: Additional project management features.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly