What are the limitations of PERT/CPM?
A
- Only allow Finish-to-Start Relationship
- Lag relationship cannot be shown
2
Q
In PERT/CPM, since it only uses a F-S relationship, the presentation of activity relationship shows that succeeding activity cannot start until its preceding activity has been completed.
A
Only allow Finish-to-Start Relationship
3
Q
If there are overlapping of activities, sometimes the approach used is through repetition of activities
A
Only allow Finish-to-Start Relationship
4
Q
-Lag is always zero
-Presence of dummy activities
A
Lag Relationship Cannot be Shown