L1.2: BASIC PERT/CPM CALCULATIONS Flashcards
1
Q
It is the earliest point in time an activity can begin
A
Early Start Time (EST)
2
Q
It is the earliest point in time an activity can finish
A
Early Finish Time (EFT)
3
Q
It is the latest point in time the activity can begin
A
Late Start Time (LST)
4
Q
It is the latest point in time an activity can finish
A
Late Finish Time (LFT)
5
Q
It is the period by which an activity can shift in its timing without affecting the Early Start of any succeeding activity
A
Free Float (FF)
6
Q
It is the period by which an activity can shift in its timing without affecting the relevant schedule of completion
A
Total Float (TF)