key revsion Flashcards
List and Describe five typical stages of a process for selection of a supplier via competitive tender
Research the companies which would be suitable for the scope of work required; this would include if they are available and if they are able to conduct the work. If they are not suitable for the task it would be a waste of time even approaching them. This could be achieved using a prequalifying questionnaire to gather information about them.
Pre-qualify this is to define a long list to a manageable number who are eligible for the contact and who would be invited to tender. Provider screening aims to reduce the likelihood of provider non performance and to ensure the provider will be responsible and respond.
Tender providers will be asked to draw bid for the work, this may proceed with RFI .or request proposals each of which are designed for providers to gain more information, the key elements is that the companies is given all the requirements are clearly defined so that providers have equal chance,
Project managers would then Shortlist potential supplies ensuring that they can achieve what the contract for, they would provide presentations, visit sites to try and win the contract.
Award contract, this involves negotiation and agreement of a contract to supply the goods and services. It is key that all parties understand that a legally binding agreement is being entered into and that the contract is not a casual nod of the head.
Within the context of earned value management, explain the term earned value management.
Earned value is a project control process based on a structured approach to planning cost collection and performance measurement, it facilitates the integration of project scope, time and cost objectives and the establishment of a baseline plan for performance measurement
Explain four benefits of using earned value management.
Project reporting.
Cost performance index and schedule performance index are two of the most commonly used key performance indicators in project management .They provide a quick and easy to understand indicator of project health,
Facilitate forecasting of outline return of cost and time,
CPI and SPI forecast can be used to project the final cost and duration of the project. Although these projections are built on assumption that future performance will continue as per past performance, they can be used to validate any competing assumptions or assertions.
Helps justify corrective action
EVM projections can act as a useful catalyst for the identification and approval of corrective action. EVM information may be used to justify a wealth of actions such as adjusting resources to the project, adding resources to the project , changing the team, revising the project scope.
May indicate early termination of the project is required.
When EVM projects that the out turn cost and time for the project render the business case no longer viable, this can lead senior management to prematurely close the project. Resources and funding can then be diverted to a more productive proposal.
List and describe five stages of a negotiation process
Plan-The first set of negotiations is planning to ensure that we can gather as much relevant information as possible, we need to identify the issues on both sides, including social and cultural interests. The project team should develop proposals on what the organisation is and what would be the best alternative to agree on, and if they fail what would be the backup plan. Need to make sure the project team thinks about both parties and what each holds and organises a united front. There is also a need for the logistical needs where when and who will host the meeting.
Discuss. With then need to establish discussion between the two parties, introductions and their roles within the project and try to establish a report. Invite the other party to establish their objectives and then state ours. Then clarify the rest of the agenda including the proposal and allow for a period of discussion between the each party if needed.
Proposing. The negation will then go to the proposing stage, proposing to the party and evaluate the reasons. Prioritising that could lead to breakdown and communicate openly so there can be no confusion in the process
Bargaining. The parties would then bargain for trade off to ensure that they get the best outcome from the negotiation, ensuring to protect the non negotiable and value any concessions made by the other party
Agreement after all negotiations have concluded both parties should summarise the outcome to ensure no confusion from the other stages, schedule follow meeting to agree the next stages if required and record all in writing so this can form the basis of a contract.
List and describe 5 typical risk management process
Initiate
initiate Identify Asses Plan Implement
Explain 5 approaches being used to conflict resolution and the circumstances under which each might be used.
Accommodate- sacrifice your own goals.
Avoid ignore the conflict
Compromise both parties obtain something but make some sacrifices
Compete higher power uses to their goals
Collaborate both parties working together to a mutually beneficial agreement
6 elements of governance
the adoption of a disciplined life cycle governance that includes approval gates at which viability is reviewed and approved
recording and communicating decisions made at approval gates
giving members of delegated bodies the capability and resources to make appropriate decisions
ensuring that business cases are supported by information that allows reliable decision-making
ensuring that stakeholders are engaged at a level that reflects their importance to the organisation and in a way that fosters trust
the deployment of suitably qualified and experienced people
Explain five distinct benefits to be gained from managing groups of projects as a programme rather than as individual, unconnected initiatives
Better prioritisation of projects in line with overall business strategy
Improved resource management and utilisation
More holistic risk management.
Increased consistency in application of project management processes
Increased shared learning across the projects within the programme
List and describe five policies which may be mentioned in a Project Management Plan
information management policy
HSE policy
HR policy, (impact on project on training recruitment, clearances)
Procurement policy (required suppliers, tendering,sourcing of good, labour)
Quality policy
list five plans normally in a Project Management Plan
The procurement plan The risk management plan The quality plan The information management plan The HSE plan describes
List and describe five ways of identifying project risks
Brainstorming Interviews Checklists. Lessons Learned Questionnaires
List and Describe five benefits of adopting a formal risk management process
Defining ways to deal with risk.
Consistency.
Allowing for contingencies.
Common reference for audit and assurance.
Sponsoring organisations have clear perspective of risk have clear perspective of risk
What are the EV calculations
CV=EV-AC
SV=EV-PC
CPI=EV\AC
SPI=EV\PC
EAC= BAC\CPI EFD = PD\SPI
6 elemtes of governance PPP
the acceptance of responsibility by the organisation’s management board for project, programme and portfolio governance
establishing clearly defined roles, responsibilities and performance criteria for governance
developing a coherent and supportive relationship between business strategy and projects, programmes and portfolios
procedures that allow a management board to call for an independent scrutiny of projects, programmes and portfolios
ensuring that project, programme and portfolio management add value
fostering a culture of improvement and frank disclosure of project, programme and portfolio information
Give 5 elements of a structured project method
- Products
- People
- Processes
- Templates
- Tools
Products are an element of a project management method. Products are what you need to deliver the project. For example, the PMP produced by the PM during definition phase. Products are also the working documents used throughout the project. These may be a risk register, a change log or a cost plan. Many of these documents i.e. drawings are held in the configuration library are version controlled, checked out and managed through the change process if they need to be amended.
People are also an element of a project management method. People are the resources working on the project, e.g. the project team, Project Manager or PMO. A method will define the standard roles and responsibilities to be used in an organisations projects. In addition to the standard roles such as project manager, sponsor and user a method may define specific company roles such as technical lead, client or project engineer.
Processes are another type of element of a project management method. The processes and procedures are produced by the Project Manager within the definition phase and form part of the Project Management Plan. The processes form a framework identifying how things need to be done and forms part of the governance of the project. This allows for continuity and structure e.g. should the project manager leave during the project it will allow someone new to take over. For example, the Risk Management Plan. This is used by the PM to monitor risk and give the ability to communicate to the Stakeholders and Users.
Templates are also an element of a project management method. They will usually have pre-determined formats and be partially populated with text of explanations for use. An example would be the Risk Register or Change Log. This provides consistency and like with processes, continuity throughout the project and more importantly through a programme of works.
Tools are an element of a project management method. These are usually items like the software used e.g. risk management software, design or reporting software. Tools can also be more specific especially during the development stage where health and safety equipment or cranes may be needed.