Key Issue 1 - Phasing of Works Flashcards
You identified h&s risks, how did you do this?
I produced a designers risk assessment which ranked risks with scores multiplied by the likelihood of them occurring, at the forefront of this was public H&S.
Given you decided to phase the works, did you offer other contractors the opportunity to re price given there was a price increase.
-Cheapest contrcat was cheaper than the second contrcator by enough that i didnt consider it would make a difference.
- I instead advised on appointing the cheapest contractor to formally develop and agreeing the phasing of works.
What were the health and safety risks associated with maintaining an operational branch?
Public access (customers and staff), increasing the risk because these people may not know how to behave on a construction site.
Safe access and egress to the construction site and branch, clearly signed to ensure no unauthorised entries.
What were the CDM implications of keeping the branch operational?
Keeping the branch operational necessitated careful adherence to CDM requirements, including updated risk assessments to include all new risks to employees and customers, health and safety plans, and robust communication to manage the impact of construction on the operational environment.
How did this impact the calculation of liquidated damages?
Delays in completing specific phases might have a direct impact on the branch’s operational efficiency and revenue, influencing the calculation of LDs based on the financial losses incurred by the client due to these delays. The complexity of maintaining operational areas may result in increased risk of delays
How did you ensure effective communication among all stakeholders throughout the phased construction process?
Effective communication was ensured through regular meetings, clear reporting, active stakeholder involvement, and robust communication channels to keep all parties informed and aligned throughout the phased construction process. This was firstly done by introducing the branch manager to the site foreman so they had a clear communicative bond.
Regarding Building Control, what elements of work were considered notifiable?
Elements considered notifiable to Building Control included major structural works, significant alterations affecting safety or compliance, modifications to safety systems, and changes impacting energy efficiency. These were identified and managed to ensure compliance with Building Regulations throughout the phased construction process.
What is a sectional completion certificate?
- Official document issued by the CA to signify that a defined section is complete.
- Shows that that section has been complete to the required standard.
What happens when a sectional completion certificate is issued?
- Rectification period begins for that section.
- Handover of that section.
- Partial release of retention proportionally.
- Client insurnace responsibility.
In what situations is sectional completion good?
- Phased projects where parts need to be handed over at certain times.
- Operational needs - where the client needs certain access to areas such as retail space to continue their operations.
How is sectional completion administered?
- Section 1.1 of JCT Contract states completion date of each section.
- Contract administrator issue sectional completion certificate for each section.
What is the impact of sectional completion for the client and contractor?
-Client - can use site, must insure if not already and still communicate with contractor regarding on going works.
-contractor - triggers rectification period for that part, partial release of retention, stops LADS for that section.
How does sectional completion impact site access?
- Contractor must still liase with client for on going works.
- Requires careful planning, which is why i implemented phasing drawings and appended to the contract.
How did you manage the H&S risk of demolishing a building, particularly the asbestos?
- Ensured a comprehensive R&D was undertaken.
- Ensured a licensed asbestos removal contrator was appointed.
- Clear segregation of the works.
- Clear signage.
- Works during off peak hours.
- Careful deconstruction, as opposed to demolition.
what measures did you put in place to ensure safety of clients staff and customers?
- Erected physical barriers to segregate works.
- clearly divided site into halfs.
- clear signage.
- regular inspections at the start of phases to ensure site set up was as per drawings.
- Ensured regular communication with client to explain up coming works.