Key Issue 1 - Chimney Flashcards

1
Q

Why could the corbelled design not be left in-situ? What change had occurred to warrant extra works?

A

Brickwork was deteriorating and was slimmer at basement level so there were fears over strength.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Did you refer to any literature to assist in identifying any signs of failure?

A

BRE Good Repair Guide 3 - Repairing Damage to Brick and Block Walls.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What was the cost and programme implication of each option?

A

Approx £3,000 cheaper and 1 week less for Option 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you specify the brickwork repairs and the ground floor structural works in the tender docs?

A

Brickwork: Referred to Good Repair Guide 3.
Floor: Structural engineer’s design portion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Did you not allow for any unforeseen works in the budget?

A

Yes £10,000 contingency, but lintels replacement used this up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did you report to the client in terms of project costs?

A

Had a schedule of interim valuations showing the costs to date and project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who had design responsibility for the altered chimney works?

A

I did (CA), as it was not part of the original Contractor’s Design Portion. [We did the design for most of the works – traditional procurement].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Aside from cost variation, did this not require extension of time to the contract programme?

A

Not with the steel support option. Other works continued while materials were ordered and installation was short (half a day).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

KI 1: If there was a delay, would an EOT be warranted if requested? Why?

A

Yes, because it was a design change from the CA and not the contractor’s fault.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you cost the three different chimney rectification methods?

A

Asked the principal contractor to provide quotes, BCIS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What RIBA stage was your project at when you had the chimney issue?

A

Stage 5 (Manufacturing and Construction).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly