Key Issue 1 - Chimney Flashcards

1
Q

Why could the corbelled design not be left in-situ? What change had occurred to warrant extra works?

A
  • Brickwork was deteriorating.
  • Walls either side being removed.
  • Thinner at bottom of breast [should be thicker].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Did you refer to any literature to assist in identifying any signs of failure?

A

BRE Good Repair Guide 3 - Repairing Damage to Brick and Block Walls.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Chimney: What was the cost and programme implication of each option?

A
  • Approx £5,000 cheaper and 1 week less for Option 3.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you specify the brickwork repairs and the suspended ground floor works in the tender docs?

A

Brickwork: Referred to Good Repair Guide 3.
Floor: Structural engineer’s design portion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Did you not allow for any unforeseen works in the budget?

A

Yes £10,000 contingency, but asbestos removal and lintels replacement used this up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who had design responsibility for the altered chimney works?

A

I did (CA), as it was not part of the original Contractor’s Design Portion.
[Structural engineer provided informal advice so their liability was limited].
[We did the design for most of the works – traditional procurement].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Chimney: Aside from cost variation, did this not require extension of time to the contract programme?

A
  • Gained time by not doing the corbelled brick repairs.
  • Other works continued while materials were ordered and installation was short (half a day).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

KI 1: If there was a delay, would an EOT be warranted if requested? Why?

A

Yes, because it was a design change from the CA and not the contractor’s fault.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you cost the three different chimney rectification methods?

A
  • Quote from principal contractor.
  • Quote from one other contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What RIBA stage was your project at when you had the chimney issue?

A

RIBA Stage 5 (Manufacturing and Construction).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When was the decision made to carry out the chimney support works?

A

3 weeks in.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you establish the time it would take to undertake these chimney works?

A
  • Got a quote from the contractor who provided time implications.
  • Reviewed the works involved and lead-in times for steel delivery to assess whether it seemed reasonable.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who was responsible for the additional steels added in to support the chimney?

A

The structural engineer agreed to provide formal advice to change it to a box structure [instead of just one steel each side of the chimney at floor level].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How did you determine whether the chimney was loadbearing or non-loadbearing?

A

The structural engineer told us it was loadbearing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Chimney: How did you verify the adequacy of the existing foundations to support additional loads from any new structural interventions?

A
  • Part of the structural engineer’s works.
  • Refurb works only - no significant weight was being added.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Chimney: How did you reassure the client about the structural safety of the final solution?

A
  • Works built according to AD A.
  • BCA signed off the works at the end of the project.