General Flashcards

(97 cards)

1
Q

How did you identify possible EPC upgrades?

A
  • Had energy consultant.
  • Insulation in suspended ground floor.
  • Double glazed sash windows.
  • Energy efficient heating and cooling unit.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you achieve an EPC B rating in a Victorian age property?

A
  • Energy efficient heating and cooling.
  • Double glazed sash windows.
  • LED lighting.
  • Insulation to suspended ground floor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Did you approve the contractor’s designs?

A
  • BCA sign off at design stage [terrace].
  • M&E signed off by M&E engineer.
  • Energy consultant sign off for EPC B.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How was the design repsonsibility split between you and the contractor?

A
  • Contractor undertook designs for the terrace and M&E.
  • I undertook design for remaining building fabric (performance spec).
  • Structural engineer: Floor structure [and chimney for KI 1].
  • Energy consultant: EPC B rating.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

a) How are sub-contracts warrantied?
b) What forms were used?

A

a) Collateral warranties.
b) JCT form (as a deed).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Chimney (KI 1): How much more would it cost to go with Option 2 rather than Option 3?

A

£5,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Chimney (KI 1): How much longer would Option 2 have taken versus Option 3?

A

Around 1 week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you report to the client in terms of project costs?

A
  • Regular meetings.
  • Payment certificates.
  • Variations [discuss and get approval from client].

[Payment certificate:
- Contract sum.
- Certified amounts to date.]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How did you deal with the variation of the works on a contractual basis?

A
  • I agreed works with the contractor.
  • Put this onto a variation order with costs.
  • Issued to contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you value the variations?

A
  • Tendered works (one other contractor).
  • Previous jobs of similar nature where possible.
    [- Cross-checked with BCIS.]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Could the contractor have refused the variation? If so, on what basis?

A

Yes, based on:
- Quantity [or quality] of the works.
- Changes to the design.
- [Site access].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How was the structural engineer appointed under the works?

A

Appointed directly through the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What would the procurement route be for Windsor Walk?

A
  • Traditional procurement route.
  • Single stage tender of 3 contractors and selected Quinn.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why did you decide to use a MW contract?

A
  • Complexity of the project.
  • JCT guide (decision tree).
    [- Traditional procurement route.]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You have stated that you prepared the preliminaries on the project, what did you include in these?

A
  • Describes the nature of the works.
  • Contract elements [IVD, LD rate, rectification period, PC date].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What information did you include in the preambles?

A

Background information and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What provisional sums did you include?

A

Asbestos discovery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What was the tender period?

A
  • 3 week tender period.
  • 3 week lead-in to begin works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What did you check regarding the contractor’s insurance?

A
  • PII (negligence).
  • Public liability (accidents).
  • All-risk (property) [covers the value of the works].
  • In-date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What were the variations on the project?

A
  • Chimney breast (originally localised repairs > structural works).
  • Flat roof repairs (originally localised repairs > overcoating roof, water ingress repairs).
  • Lintels to basement (contract instruction).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What was your role for releasing the retention at Windsor Walk?

A

I released 2.5% on PC. [2.5% released when Making Good Certificate issued but I left Hollis before that].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Is the Contractor’s Design Portion optional?

A

Yes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What stage did you do the design to?

A

Stage 4 (Technical Design).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Can you provide an example of an instruction on Windsor Walk?

A
  • Chimney structural works.
  • Lintels replacement.
  • Removal of graffiti.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Note: AD A (structure). AD L (EPCs, heating and cooling - conservation of fuel and power). AD M (accessibility). AD H (flat roof and pipework – drainage and waste disposal).
26
Note: Liquidated Damages could not be claimed by the client as they had suffered no direct loss. These were set at £1,000 per week in the contract, calculated as the loss suffered by the client from future rent.
27
Why was the project over budget?
- Chimney issue. - Lintels issue. - Asbestos removal.
28
How did you ensure the Contractor's Design Portion was built correctly?
- Sent drawings to BCA to ensure they met building regs [terrace - AD A, AD K (guard rails)]. - Final Certificate, M&E engineer and EPC consultant sign off. [As long as you can show it meets requirements you don't need to conduct a check of their designs e.g. building regs, EPC consultant - send details to them for them to check certificates and sign off.]
29
How was the budget cost calculated?
- Costs from previous projects of a similar nature. - BCIS [cross-checked with BCIS].
30
Note: Liquidated damages sum: £1,000 per week [not required on this project].
31
The extension of time – was that a Relevant Event or Matter?
It's not referred to a Relevant Event in a Minor Works contract - called Extension of Time. [Relevant Event is related to an Extension of Time. Relevant Matter related to loss and expense claim.]
32
What would you have done if the time claimed by the contractor was deemed excessive?
Complete my own assessment of the time required and feed it back to the contractor if it was less.
33
What were the implications when the BSA came into force during the project?
Act partly came into force in June 2022 and fully in October 2023. Not much impact as not HRB. [Building safety regulator, accountable person].
34
Why was Variable Refrigerant Flow (VRF) used instead of Variable Air Volume (VAV)?
It's more energy efficient.
35
Please explain the contractor dispute in more detail. Had they not realised the extent of the works required at tender issue?
- Didn't price for some of the works despite it being in the spec. - Allowed for ad hoc repairs but needed liquid repairs and fixing water run off detail at the rear.
36
Flat roof works dispute: What works had the contractor included in the tender and what works had the contractor not allowed for?
Allowed for the works but underpriced it.
37
You mentioned that the contractor claimed costs which had increased since tender stage. Does the form of contract used deal with cost fluctuation in any way?
- MW: No - contract amendment required. - IC: Included if selected (not included by default but contract allows for them).
38
Contractor attempting to claim costs for variations: Did the contractor accept the fault or dispute it further?
They accepted that they had not priced it correctly and that the works were in the spec.
39
1) Who designed the M&E works on the project? 2) How did you check the works were correct if you're not an M&E consultant?
1) This was part of the contractor’s design portion. 2) M&E engineer appointed direct to client - produced spec and checked works.
40
What piece of legislation do the MEES (Minimum Energy Efficiency Standards) ratings derive from?
The Energy Act 2011.
41
Who was the Principal Designer (BSA) on the project?
External consultant appointed by the client. [Not competent to fulfil this role]. Not required - required from October 2023 onwards (PC was 20 September).
42
How did you establish the brief with the client?
- Inspected the site together. - Took notes, photos. - Confirmed in writing. - Wrote spec. - Discussed with planning consultant. [Refurbishment, ground floor structure, EPC B rating.]
43
What information could you have used to develop the client's brief?
O&M manuals [none available on this job].
44
What advice did you give regarding fire safety in terms of design?
- Must comply with AD B. - Fire escape door widths - 750mm. [Actual width 775mm, 1000mm - new build]
45
You said as part of the client's brief the property had to be accessible, what legislation or regulations were you working to?
- Equality Act 2010. - Approved Document M. - BS 8300.
46
What provisions were there to ensure the property was accessible?
- Accessible WC. - Ramps (level access). - Doors were wide enough (AD M) [775mm fire escape, 800mm WC].
47
Windsor Walk: Talk me through the build-up of the flat roof.
- Warm roof: Deck, vapour control layer, insulation, covering. - Cold roof: Plasterboard, vapour control layer, insulation (between beams), deck, covering. - Inverted: Deck, covering (asphalt), insulation, membrane, ballast/concrete slabs. [Vapour control layer always goes before insulation.]
48
1) Did you write the specification? 2) What did you use to write this?
- Yes. - Drawings from planning application. - NBS Chorus. - BS 8000. - Previous jobs of a similar nature.
49
- Was planning permission required and were you involved? - What did planning permission involve?
- Yes required, I wasn't involved (client did this prior to my company's involvement). - Change of use to cafe. - New windows.
50
Was the lime plaster applied to lath and plaster? What technique is used to apply the lime plaster?
- No, masonry [no hair required within the plaster as it was applied to masonry not lath and plaster]. - 3 coat system.
51
What was: - Contract sum. - Final account. - Contingency (% and £). - Contractor prelims. - LDs. - Tender period and lead in.
- Contract sum: £243k. - Final account: £260k. - Contingency (% and £): 4.5% and £10,000. - Contractor prelims: £3,000 p/week. - LDs: £1,000 p/week. - Tender period and lead in: 3 weeks for each.
52
Did you need consent from Network Rail?
Yes, produced a small report detailing works with photos.
53
How were you appointed?
- Single stage tender. - Submitted lump sum cost - percentage of the works at 10%. [I wasn't involved in this process - chartered suveryor].
54
- What was the manufacturer of the floor insulation? - What was the thickness of the floor insulation? - What was the U-value of the floor insulation?
- Knauf. - 150mm. - 0.16W/m2K.
55
The chimney appears to have damp staining to the outside. What could have caused this?
- Poor ventilation (fire place no longer in use). - Warm air from building could condense on the chimney when it meets cold air outside.
56
What were the range of tenders?
£243k-£270k.
57
How did you assess whether the contractor's were competent?
- CHAS (Contractors Health and Safety Assessment Scheme). - Constructionline [finances, H&S]. - PII.
58
What were the main costs on the project and what were the amounts?
- Ground floor £15k. - Windows £35k.
59
Note: - Basement walls - lime plaster. - Floor joists - 400mm centres.
60
What manufacturer did you use for the liquid repairs to the flat roof?
Sika - 2 coats.
61
a) What was the insurance option selected? b) What was the benefit of this? c) What happens at Practical Completion?
a) - Insurance for existing structures (option C). b) - Suitable for refurb projects, insures existing structure [no disputes if existing structure is damaged]. c) - Insurance responsibility passes to the client [starts as joint names - client and contractor].
62
What was the cause of the cracking to the brick arches?
Arch failure (undertook research to ascertain if this was arch failure - cracking to corner of the arches, dropped bricks).
63
What Approved Documents did you use for the air conditioning unit with heat pump?
- AD F (ventilation) [fan]. - AD L (conservation of fuel and power).
64
Why did the final account differ from the contract sum?
- Variations: chimney breast, lintels. - Asbestos provisional sum not enough (£1500 allowed but was £8k).
65
Who was PD? How did they manage the risk of the dilapidated state of the building?
- Chartered surveyor who supervised on the project. - RA. - PCI. - Requested building information from the client.
66
What RIBA stage did you prepare your specification to?
RIBA Stage 4 - Technical Design.
67
What was the existing use of the property? What was the planning use class changed to?
- Office. - Class E(b).
68
Who was responsible for discharging the planning conditions?
- The client. - Contractor follows planning conditions on-site.
69
What stage did you prepare the M&E specification to?
RIBA Stage 3 - Spatial Coordination. [Going to Stage 4 Technical Design would mean I wrote the spec detailing how they completed these works which wouldn't make sense if they were completing the design of this element of works]
70
What years does the Victorian era span?
1837-1901.
71
What did you include in the tender documents?
- SoW. - Prelims. - Materials and Workmanship. - Form of Tender. [- PCI (appended).]
72
Windsor Walk: Where was the condenser and FCU positioned?
- FCU - above ceiling. - Condenser - no condenser only 2 holes for vents in parapet wall.
73
You said that Windsor Walk is in a conservation area. What is an Article 4 direction?
When a council removes permitted development rights. [Works can still go ahead but must have planning permission]
74
What conservation area is Windsor Walk in?
Camberwell Grove.
75
If the M&E engineer is producing the specification what would the contractor be designing as part of the contractor's design portion?
- Develop detailed design. Select specific items e.g: - Ductwork layout. - Size of plant and pipework. - Cable size and routes.
76
Windsor Walk: a) Did you require planning permission for the works? b) Were there any special planning considerations?
- Yes, planning consultant instructed due to conservation area and Listed building. - Conservation area [external features to match proposed drawings e.g. sash windows]. - Heritage statement [historical significance, impact assessment]. - Design and Access Statement. - Noise assessment - heating and cooling unit [not needed as no neighbouring residential properties and installed inside and not on party wall]. [External unit for heating and cooling not required - external ventilation only to flat roof]
77
What building regulations applied to the flat roof works?
- AD L: more than 50% of covering being replaced. - AD H: drainage. - AD B: BROOF(t4) [liquid repair].
78
Windsor Walk: When advising the client on the brickwork repairs, what other considerations did you take into account?
- Lime mortar to be used. - Structure. [- Scaffolding.]
79
Windsor Walk: What was the value of the variations?
£35k.
80
Was the project notifiable under CDM Regulations 2015?
Yes, exceeded 500 person days. [No. of workers x no. of working days]
81
Can you talk me through the planning process?
- Submit LBC and planning applications. - Consultation period (neighbours, Historic England can submit comments) [21 days]. - Decision [approx 8 weeks].
82
What was included in the planning application?
- Full planning permission. - Listed Building Consent. - Change of use.
83
What steps did you take to ensure compliance with listed building regulations?
- Spoke to planning consultant. - Planning consultant discussed designs with conservation officer. - LBC was granted before starting works. - Works completed according to proposals.
84
What would you do if the contractor deviated from approved plans?
- Stop works. - Apply for retrospective planning [if required]. - Discuss with planning consultant.
85
What risks are associated with carrying out works on a Listed building without consent?
- Prison [criminal offence]. - Fine [unlimited]. - Reverse works. - Negligence claim [from client].
86
What role does a Design and Access Statement play in planning for listed buildings?
- Details rationale behind design. - States how access is addressed.
87
Windsor Walk: Was Listed Building Consent required for the structural works to the chimney breast after discovering the corbelled design?
It can be but planning consultant advised it wasn't necessary following discussions with conservation officer.
88
Windsor Walk: Why did you choose a single stage tender route?
- Design already complete [no need for contractor input (two stage)]. - Competitive pricing [all tenders submitted at once].
89
Windsor Walk: What would you need to consider before removing the lime plaster?
- Horse hair (anthrax). - Mask and gloves to be worn.
90
What planning documents are included for a Listed building in a conservation area?
- Location plan. - Existing and proposed plans. - Heritage statement. - Design and Access statement [more focused on conservation area]. - Photos.
91
How did you assess whether the structural engineer was competent? What documents could you have viewed?
- Constructionline. - Insurance [PII, public liability, all risk]. - Registered with professional body i.e. IStructE.
92
How did you ensure your specification complied with heritage constraints?
- Planning consultant liaised with conservation officer [then fed back to me]. - Materials in keeping with original e.g. lime mortar, sash windows.
93
Windsor Walk: What fire rating would the steel beam to the ground floor need?
60 minutes.
94
Windsor Walk: Can you explain the planning process you undertook for the LBC in terms of getting the designs approved?
- Wrote spec [BS 7913]. - Discuss with planning consultant [to ensure proposed works would be approved from heritage perspective]. - Planning consultant [discussed with conservation officer]. - Submit for LBC. - Undertake works.
95
Windsor Walk: What are some typical defects with artificial slates?
- Cracking. - Moss and lichen growth. - UV damage.
96
Are there any considerations in terms of weight with artificial slates?
Artifical slates are light and can lift in the wind.
97
Windsor Walk: What considerations were there for using lime plaster?
- Drying time. - Anthrax (horse hair). - Breathable [apply on lime mortar not cement mortar].