General Flashcards
(97 cards)
How did you identify possible EPC upgrades?
- Had energy consultant.
- Insulation in suspended ground floor.
- Double glazed sash windows.
- Energy efficient heating and cooling unit.
How did you achieve an EPC B rating in a Victorian age property?
- Energy efficient heating and cooling.
- Double glazed sash windows.
- LED lighting.
- Insulation to suspended ground floor.
Did you approve the contractor’s designs?
- BCA sign off at design stage [terrace].
- M&E signed off by M&E engineer.
- Energy consultant sign off for EPC B.
How was the design repsonsibility split between you and the contractor?
- Contractor undertook designs for the terrace and M&E.
- I undertook design for remaining building fabric (performance spec).
- Structural engineer: Floor structure [and chimney for KI 1].
- Energy consultant: EPC B rating.
a) How are sub-contracts warrantied?
b) What forms were used?
a) Collateral warranties.
b) JCT form (as a deed).
Chimney (KI 1): How much more would it cost to go with Option 2 rather than Option 3?
£5,000.
Chimney (KI 1): How much longer would Option 2 have taken versus Option 3?
Around 1 week.
How did you report to the client in terms of project costs?
- Regular meetings.
- Payment certificates.
- Variations [discuss and get approval from client].
[Payment certificate:
- Contract sum.
- Certified amounts to date.]
How did you deal with the variation of the works on a contractual basis?
- I agreed works with the contractor.
- Put this onto a variation order with costs.
- Issued to contractor.
How did you value the variations?
- Tendered works (one other contractor).
- Previous jobs of similar nature where possible.
[- Cross-checked with BCIS.]
Could the contractor have refused the variation? If so, on what basis?
Yes, based on:
- Quantity [or quality] of the works.
- Changes to the design.
- [Site access].
How was the structural engineer appointed under the works?
Appointed directly through the client.
What would the procurement route be for Windsor Walk?
- Traditional procurement route.
- Single stage tender of 3 contractors and selected Quinn.
Why did you decide to use a MW contract?
- Complexity of the project.
- JCT guide (decision tree).
[- Traditional procurement route.]
You have stated that you prepared the preliminaries on the project, what did you include in these?
- Describes the nature of the works.
- Contract elements [IVD, LD rate, rectification period, PC date].
What information did you include in the preambles?
Background information and objectives.
What provisional sums did you include?
Asbestos discovery.
What was the tender period?
- 3 week tender period.
- 3 week lead-in to begin works.
What did you check regarding the contractor’s insurance?
- PII (negligence).
- Public liability (accidents).
- All-risk (property) [covers the value of the works].
- In-date.
What were the variations on the project?
- Chimney breast (originally localised repairs > structural works).
- Flat roof repairs (originally localised repairs > overcoating roof, water ingress repairs).
- Lintels to basement (contract instruction).
What was your role for releasing the retention at Windsor Walk?
I released 2.5% on PC. [2.5% released when Making Good Certificate issued but I left Hollis before that].
Is the Contractor’s Design Portion optional?
Yes.
What stage did you do the design to?
Stage 4 (Technical Design).
Can you provide an example of an instruction on Windsor Walk?
- Chimney structural works.
- Lintels replacement.
- Removal of graffiti.