General Flashcards

1
Q

Why do you believe you’re competent to be a Principal Designer (CDM)?

A

Technical knowledge and experience, design involvement allows me to compile PCI and plan works with the principal contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you identify possible EPC upgrades?

A

External consultant was used to advise on this, who suggested including the AC unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you achieve an EPC B rating in a Victorian age property?

A

Energy efficient AC (heating and cooling), double glazed sash windows, LED lighting, insulation to suspended ground floor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Did you approve the contractor’s designs?

A

Got Building Control Approver sign off at design stage. I reviewed the energy consultant’s sign off to be sure it achieved EPC B.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How was the design repsonsibility split between you and the contractor?

A

I wrote a performance spec for the building fabric and the contractor undertook designs for the M&E and terrace.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How are sub-contracts warrantied? What forms were used?

A

Collateral warranties.
JCT form (as a deed).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the current MEES ratings and their dates?

A

C - 2028, B - 2030, net zero - 2050.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How much more would it cost to go with Option 2 rather than Option 3?

A

£3,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How much longer would Option 2 have taken versus Option 3?

A

Around 1 week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you report to the client in terms of project costs?

A

Had a schedule of interim payment certificates showing the costs to date and contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you deal with the variation of the works on a contractual basis?

A

I agreed the works with the contractor, put this onto a variation order with costs, issued to contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you value the variations?

A

Got additional quotes to compare costs, checked BCIS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Could the contractor have refused the variation? If so, on what basis?

A

Yes, based on changes to the design, quality or quantity of the works, [or site access].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How was the structural engineer appointed under the works?

A

Appointed on the client’s side. [Direct to client or contactor.]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How was the structural engineer’s appointment arranged?

A

Appointed directly through the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What would the procurement route be for Windsor Walk?

A

It was a traditional procurement route, single stage tender of 3 contractors and selected Quinn.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why did you decide to use a MW contract?

A

Because of the contract value being around £250k, complexity of the project, traditional procurement route.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

You have stated that you prepared the preliminaries on the project, what did you include in these?

A

Described the nature of the works and how these should be carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What information did you include in the preambles?

A

Background information and objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What provisional sums did you include?

A

Asbestos discovery.

21
Q

What was the tender period?

A

2 week tender period and 3 week lead-in to begin works.

22
Q

What did you check regarding the contractor’s insurance?

A

PI (negligence), public liability (accidents), all-risk (property) [covers the value of the works], in-date.

23
Q

What were the variations on the project?

A

Chimney breast (originally localised repairs > structural works), flat roof repairs (originally localised repairs > overcoating roof, water ingress repairs).
Lintels to basement (contract instruction).

24
Q

What was your role for releasing the retention at Windsor Walk?

A

I released 2.5% on PC. [2.5% released when Making Good Certificate issued but I left Hollis before that].

25
Q

Is the Contractor’s Design Portion optional?

26
Q

What stage did you do the design to?

A

Stage 4 (Technical Design).

27
Q

Can you provide an example of an instruction on Windsor Walk?

A

Removal of graffiti.

28
Q

Note:
AD A (structure).
AD L (EPCs, air conditioning - conservation of fuel and power).
AD M (accessibility).
AD H (flat roof and pipework – drainage and waste disposal).

29
Q

Note: Liquidated Damages could not be claimed by the client as they had suffered no direct loss. These were set at £1,000 per week in the contract, calculated as the loss suffered by the client from future rent.

30
Q

Why was the project over budget?

A

Chimney and lintels issue.

31
Q

How did you ensure the Contractor’s Design Portion was built correctly?

A

Contractor issued drawings which were forwarded to the Building Control Approver to ensure they met building regs.
Final Certificate and EPC consultant sign off.
[As long as you can show it meets requirements you don’t need to conduct a check of their designs e.g. building regs, EPC consultant - send details to them for them to check certificates and sign off.]

32
Q

How was the budget cost calculated?

A

Costs from previous projects of a similar nature, BCIS [cross-checked with BCIS].

33
Q

Note: Liquidated damages sum: £1,000 per week [not required on this project].

34
Q

The extension of time – was that a relevant event or matter?

A

Relevant Event is related to an Extension of Time.
Relevant Matter related to loss and expense claim.

35
Q

What would you have done if the time claimed by the contractor was deemed excessive?

A

Complete my own assessment of the time required and feed it back to the contractor if it was less.

36
Q

What were the implications when the BSA came into force during the project?

A

Act partly came into force in June 2022 and fully in October 2023. Not much impact as not HRB. [Building safety regulator, accountable person].

37
Q

Why was Variable Refrigerant Flow (VRF) used instead of Variable Air Volume (VAV)?

A

It’s more energy efficient.

38
Q

Please explain the contractor dispute in more detail. Had they not realised the extent of the works required at tender issue?

A

Didn’t price for some of the works despite it being in the spec, cost of materials had increased so they wanted more fees.

39
Q

Flat roof works dispute: What works had the contractor included in the tender and what works had the contractor not allowed for?

A

They allowed for the flat roof works but underpriced it [underestimated the extent of repairs required].

40
Q

You mentioned that the contractor claimed costs which had increased since tender stage. Does the form of contract used deal with cost fluctuation in any way?

A

There’s no provision for cost fluctuations in MW contracts.

41
Q

Contractor attempting to claim costs for variations: Did the contractor accept the fault or dispute it further?

A

They accepted that they had not priced it correctly and that the works were in the spec.

42
Q

Who designed the M&E works on the project?

A

This was part of the contractor’s design portion.

43
Q

What piece of legislation do the MEES (Minimum Energy Efficiency Standards) ratings derive from?

A

The Energy Act 2011.

44
Q

Who was the Principal Designer (BSA) on the project?

A

Not required - required from October 2023 onwards (PC was 20 September).

45
Q

How did you establish the brief with the client?

A

Inspected the site together.
Took notes, photos.
Confirmed in writing.
[Refurbishment, ground floor structure, EPC B rating.]

46
Q

What information could you have used to develop the client’s brief?

A

O&M manuals [none available on this job].

47
Q

What advice did you give regarding fire safety in terms of design?

A

Fire escape door widths (775mm, 1000mm - new build).

48
Q

You said as part of the client’s brief the property had to be accessible, what legislation or regulations were you working to?

A

Equality Act 2010, Approved Document M.

49
Q

What provisions were there to ensure the property was accessible?

A

Accessible WC, ramps (level access), doors were wide enough (AD M).