Investment appraisal techniques 2.0 Flashcards

QB Tips

1
Q

How is DPP calculated and what is the the general proforma to use ?

A

Based on cumulative discounted cash flows.
Proforma:
Year CF DF Cumulative. D.CF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the effect of increasing cost of capital on IRR and DPP ?

A

IRR: No change
DPP: Increases !

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why does an increase in cost of capital increase DPP ?

A

Reduces future cash inflows, increases time taken for cumulative discounted cash flows to become positive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the decision rules for IRR ?

A

IRR > Cost of capital, ACCEPT
IRR < Cost of capital, REJECT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the method for finding an appropriate cost of capital for projects with different IRRs ?

A

Step 1 - Draw graphs, paying attention to positive / negative cumulative cash flows.
Step 2 - Test where each cost of capital would give a positive NPV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you calculate ARR when given cash flows of a depreciating asset ?

A

Must subtract the depreciation from the cash flows to get profit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you calculate the PV of a perpetuity (discounting perpetuities) ?

A

PV = Cash flow / r

(even if r changes)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an example of an Appraisal cost ?

A

Testing and Inspecting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate an Advanced annuity when there is an initial cash outlay, constant annual cash flows and a final cash outlay ?

Look for keyword: Immediately

A

(1) NPV of initial cash outlay:
Y0 : Net cash flow = Initial outlay + annual inflow.
(2) NPV of constant cash inflows:
Use table for N - 1 year (4th column)
NPV = annual cash flow x AF.
(3) NPV of final cash outlay:
Use table for N years (3rd column)
NPV = final outlay x DF
(4) Add together !

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

If there are two ‘normal’ (not mutually exclusive) projects, what comments can be made about IRR and NPV ?

A

There will be no conflict between the two techniques.
IRR and NPV may not rank the projects in the same order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the effect of an increase in cash flows on IRR and PP ?

A

No change will occur to PP.
IRR will increase due to higher cash flows require greater costs of capital to make NPV = 0.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you calculate the NPV of delayed cash flows ?

A

Calculate NPV as normal but ignore payment at T0.
Use n = 1 as first DF.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some examples of external failure costs ?

A

Cleaning contaminated soil.
Government penalties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you calculate PP when given profits instead of cash flows from a depreciating asset ?

A

Add the depreciation back to profits to get cash flows, continue as normal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate NPV when there is a change in cost of capital ?

A

In the year that cost of capital changes,
DF = 1 / [( 1 + r1 ) x ( 1 + r2 )]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What comment can be made if a project has a unique IRR and the IRR is more than the cost of capital ?

A

IRR will give too much weight to later cash flows.

17
Q

How is Terminal value calculated using NPV ?

A

NPV = NTV x DF , where n is the life of the project.

18
Q

How is the IRR of a perpetuity calculated ?

A

IRR = Annual inflow / Initial investment x 100

19
Q

If projects all have the same initial outflow, constant annual inflows and the same lives, How will they be ranked based on NPV, PP and IRR ?

A

NPV and PP will give same ranking.
IRR and PP will give same ranking.
NPV and IRR will NOT give same ranking.