Introduction Cont Flashcards

1
Q

What are the 5 life cycle types?

A
  1. Predictive (Waterfall)
  2. Iterative
  3. Incremental
  4. Adaptive (Agile)
  5. Hybrid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What life cycle type would you use for complex or unique project?

A

Predictive. ie Mars Rover

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What project life cycle type has maximum flexibility?

A

Hybrid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 5 Project Management Process Groups?

A
  1. Initiating
  2. Planning
  3. Executing
  4. Monitoring and Controlling
  5. Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Project Phases?

A

A collection of logically related project activities that culminates in the completion of one or more deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are Phase Gates?

A

A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification or to end a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a process?

A

A systematic series of activities directed towards causing an end result such that one or more inputs will be acted upon to create one or more outputs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 10 Knowledge areas?

A
  1. Integration Management
  2. Scope Management
  3. Schedule Management
  4. Cost Management
  5. Quality Management
  6. Resource Management
  7. Communication Management
  8. Risk Management
  9. Procurement Management
  10. Stakeholder Management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the business case?

A

A documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition and that is used as basis of authorization of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 4 major components of the business case?

A
  1. Business Needs
  2. Analysis
  3. Recommendations
  4. Evaluation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the project benefits management plan?

A

A document that describes how and when the benefits of the project will be delivered, and describes the mechanisms that should be in place to measure those benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 7 major components of the Project Benefits Management Plan?

A
  1. Target benefits
  2. Strategic alignment
  3. Timeframe for realizing benefits
  4. Benefits owner
  5. Metrics
  6. Assumptions
  7. Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Project Charter?

A

A document issued by the project sponsor that formally authorized the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the Project Management Plan?

A

Document that describes how the project will be executed, monitored and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Benefits Realization Management?

A

Collective set of processes and practices for identifying benefits and aligning them with formal strategy ensuring benefits are realized as project implementation progresses and finishes, and that the benefits are sustainable and sustained after project implantation is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the Benefits Realization Plan?

A

A document outlining the activities necessary for achieving the planned benefits. It identifies a timeline and the tool and resources necessary to ensure the benefits are fully realized over time.

17
Q

What is the Benefits Management Plan?

A

The documented explanation defining the process for creating, maximizing and sustaining the benefits provided by a project or program.

18
Q

What are the three phases of a benefits management plan?

A
  1. Identify Benefits
  2. Execute to the benefits
  3. Sustain the benefits
19
Q

What is a constraint?

A

A limiting factor that affects the execution of a project, program, pro folio or process.

20
Q

What are the 6 constrains types?

A
  1. Scope
  2. Schedule
  3. Cost
  4. Quality
  5. Resource
  6. Risk
21
Q

What are the three types of reviews?

A
  1. Customer service review
  2. Sponsor Project Review
  3. Peer Project Review