A schedule has deliverable milestones defined for only the first three months of the project. The project manager intends to provide a more detailed schedule as the work progresses, following a more thorough understanding of the project. This approach to project planning is called:

a. Planning
b. Life cycling
c. Progressive elaboration
d. Requirements evaluation

A

C. Progressive elaboration is the iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

navigate. When considering sunk costs, which of the following best defines the situation?
a. It is a cost that hasn’t been incurred by selecting one project over another.
b. It is a cost that has been incurred by selecting one project over another.
c. It is a cost that has already been incurred but can still be recovered.
d. It is a cost that has already been incurred and cannot be recovered.

A

D. A sunk cost is money that an organization has already spent and, because it cannot be recovered, should not be factored into future expenditures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which financial measurement identifies how soon you will recapture your investment and start making a profit?

a. Benefit-cost ratio
b. Payback period
c. Net Present Value
d. Sunk costs

A

B. The payback period calculates the initial investment and the estimated income over time to determine when you should recapture your investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Determining if a project aligns with a company’s Key Performance Indicators as part of the project selection process refers to which project selection variable?

a. Expected financial benefit
b. Available funding
c. Strategic alignment
d. Riskiness of the project

A

C. Strategic alignment is a key variable factored in the project selection process and examines if a project aligns with a company’s strategic plan and Key Performance Indicators.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which tool and technique group has techniques used to organize, assess and evaluate data and information?

a. Data analysis technique
b. Data representation techniques
c. Data gathering techniques
d. Decision-making techniques

A

A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You work for a nationally owned construction company and you’ve been asked to work on a project in Florida during August and September. Which EEF should you be concerned about?

a. Company culture
b. Weather
c. Resource availability
d. Infrastructure

A

b. August and September are not only very hot in Florida, they are right in the middle of hurricane season, and therefore weather would be a concern.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
If an organization finds that it lacks the necessary skilled resources to create all the deliverables that are required for a project, it may need to implement the Project \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_ Management processes.
Stakeholder
Scope
Schedule
Procurement
A

D. By definition, Project Procurement Management includes the processes necessary to purchase or acquire products, services, or results needed from outside the project team or performing organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If the organization does not have all the skills or capacity to perform all the activities or create all the deliverables that are necessary, you may need to implement Project ________ Management processes.

a. Stakeholder
b. Time
c. Procurement
d. Scope

A

Project Procurement Management includes the processes necessary to purchase or acquire the products, services, or results needed from outside the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the value of the best alternative choice that was not taken when, given limited resources, a choice needs to be made between two or more mutually exclusive alternatives?

a. Sunk cost
b. Incurred cost
c. Opportunity cost
d. Recoverable cost

A

C. Opportunity cost is incurred by selecting one project instead of another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Sequence Activities is part of the ______ process group and correlates to the Project ________ Management knowledge area

a. Planning; Schedule
b. Initiating; Scope
c. Executing; Stakeholder
d. Initiating; Risk

A

a. Sequence Activities is a process categorized under the Planning process group. This process correlates to the knowledge area of Project Schedule Management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following describes an individual in a management role within a functional area of the organization that has their own permanent staff responsible for the ongoing work?

a. Project manager
b. Program manager
c. Functional manager
d. Portfolio manager

A

The best answer choice is C. The functional manager has a permanent staff responsible for carrying out the ongoing work of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following is NOT one of the competing constraints as defined by PMI?

a. Quality
b. Scope
c. Schedule
d. Customer Request

A

D. The competing constraints include scope, schedule, quality, cost, resources, and risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

After documenting the project life cycle, determining how performance will be measured, identifying EEFs, and prioritizing project constraints, it may be possible to complete the:

a. Project management plan
b. Project charter
c. Scope management plan
d. Project scope statement

A

A. These activities would be included in the Planning process group, resulting in a project management plan as the output

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Managing a work effort that is made up of a group of related projects is an example of what?

a. Program
b. Project
c. Portfolio
d. Strategic initiative

A

A. The definition of a program is a group of related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You are planning a project where you intend to complete one phase and obtain customer sign-off before initiating the next phase. This is an example of which project life cycle?

a. Overlapping
b. Iterative
c. Sequential
d. Fast tracking

A

C. A sequential life cycle phasing approach requires that you complete one phase of a project before initiating the next

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

You’re setting up your project and need to manage it so that you complete one phase and get customer sign-off before beginning the next phase. What type of project life cycle should you use?

a. Overlapping
b. Sequential
c. Fast tracking
d. Iterative

A

B. A sequential project life cycle requires you to complete one phase before initiating the next phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

During a company retreat, a team of employees brainstormed about ways to improve the efficiency and accuracy of the system for paying part-time employees and independent contractors. The company approved the changes, which will be phased in over the next year. This would be an example of which reason for initiating a project according to the PMBOK® Guide?

a. Business need
b. Market demand
c. Customer request
d. Material issues

A

A. This is an example of a project that creates, improves, or fixes a product, process, or service for the business.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What would be the output after completing the following activities: documenting the project life cycle, determining how performance will be measured, identifying EEFs, and prioritizing project constraints?

a. Project management plan
b. Project charter
c. Scope Management plan
d. Project scope statement

A

a. These activities would be included in the Planning process group resulting in a project management plan as the output.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Which of the following is NOT an organizational process asset?

a. Defect database
b. Information from past projects
c. Change control procedures
d. Organizational Culture

A

D. Organizational culture is an enterprise environmental factor (EEF).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

There are several financial calculations used to evaluate potential projects. Which of the following evaluation techniques takes the present value and deducts the initial costs and ongoing expenditures?

a. Net present value
b. Future value
c. Payback value
d. Cost/Benefit

A

A. Net present value (NPV) takes the present value and subtracts the cost of the initial and ongoing investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

During a year-end company performance review meeting, several associates provide feedback that an automated timekeeping system would greatly improve the speed of client billing. Senior management immediately approves the formation of an ad-hoc committee to provide guidance and offer suggestions for implementation. According to the PMBOK® Guide, this would be an example of which project initiator?

a. Legal requirement
b. Customer request
c. Organizational need
d. Social need

A

C. Examples of organizational need projects include process improvement, relocations, reorganizations, or any project undertaken to improve the efficiency and overall effectiveness of the performing organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A newly procured contract requires an aluminum welder, a specialized resource not currently staffed at your company. This EEF is an example of which of the following?

a. Company culture
b. Procurement
c. Availability of resources
d. Weather

A

C. A specialized resource not readily available within the performing organization is an example of an EEF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The custom homebuilder you work for has a contract to build a home. The customer wants marble from Florence, Italy. To work with the tile, you need extremely skilled craftspeople with special tools. This EEF is an example of

a. Company culture
b. Infrastructure
c. Weather
d. Availability of resources

A

D. The material and the labor to work with it are constraints associated with the availability of resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Which is the best description of a controlling PMO operating within an organization?

a. Only manages large, complex projects
b. Requires mandated compliance with the project management methodology
c. Serves as a project repository for all project management resources
d. Maintains a high degree of control

A

B. A controlling PMO develops policies, procedures, templates, forms, and reports for project management and requires compliance with the project management methodology prescribed by the performing organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
Defining activities, sequencing activities, and estimating activity durations are all part of Project \_\_\_\_\_\_\_\_\_\_\_\_\_\_ Management processes.
Scope
Schedule
Cost
Quality
A

B. Project scheduling provides a detailed plan that represents how and when the project will deliver the products, services, and results defined in the project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the definition of the term “project”?

a. A temporary endeavor undertaken to create a unique product, service, or result
b. A function or a series of steps and actions that support the business or a stakeholder
c. An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item
d. An output from performing project management processes and activities

A

A. A project is a temporary endeavor undertaken to create a unique product, service, or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

The Project Management process groups include which of the following?

a. Integration, Scope, Risk, Quality, Time
b. Initiating, Planning, Executing, Monitoring and Controlling, Closing
c. WBS, WBS Dictionary, Network Scheduling Diagram, Critical Path
d. Plan Scope, Create Requirements, Define Scope, Create WBS

A

The best answer choice is B because it contains the five process groups.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

A temporary endeavor undertaken to create a unique product, service, or result is the definition of what?

a. Program
b. Project
c. Portfolio
d. Strategic initiative

A

B. The PMBOK® Guide definition of a project is a temporary endeavor undertaken to create a unique product, service, or result.

29
Q

navigate. What is an input?
a. Something tangible used in performing an activity to produce a product or result
b. A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service
c. A systematic series of activities directed toward causing an end result
d. Any item, whether internal or external to the project, that is required by a process before that process proceeds

A

D. An input is any item, whether internal or external to the project, that is required by a process before that process proceeds. It may also be an output from a predecessor process

30
Q

Validate Scope is part of the Project ________ Management Knowledge Area required for the ________ process group.

a. Time; Planning
b. Communications; Executing
c. Quality; Initiating
d. Scope; Monitoring and Controlling

A

D. Validate Scope is a process categorized in the knowledge area of Project Scope Management and is part of the Monitoring and Controlling process group.

31
Q

Which of the following is characteristic of a matrix organization?

a. An interdisciplinary team performs the project.
b. The organization is separate from functional departments.
c. The PM has full authority and responsibility.
d. The functional department performs the project.

A

A. An interdisciplinary team performs the project. In matrix organizations, team members from different departments work on the project

32
Q

When concerned with workflows that are costly or ineffective, an organization will focus on which of the following nonfinancial metrics?

a. Process improvement
b. Customer retention
c. Employee satisfaction
d. Future opportunities

A

A. Process improvement, which is the act of increasing the efficiencies of organizational procedures, is a common nonfinancial metric that organizations will consider.

33
Q

A schedule has milestones listed with only the first 90 days’ worth of work defined in detail. The project manager will provide a more detailed schedule as the project progresses, when he has a greater understanding of what is involved. This is called

a. Planning
b. Life cycle planning
c. Progressive elaboration
d. Progressive estimating

A

C. Progressive elaboration is continuing to provide more detail as more is known about the project.

34
Q

Project Alpha has a benefit-cost ratio of 1.1:1, Project Beta has a benefit-cost ratio of 1.33:1, and Project Charlie has a benefit-cost ratio of 1.17:1. Using a financial analysis, which project is the best investment?

a. Not enough information to determine the answer
b. Project Alpha
c. Project Beta
d. Project Charlie

A

C. Project Beta has the best benefit-to-cost ratio.

35
Q

Which of the following metrics would be the most useful in looking at the reward or income of a project and comparing it with the project’s expenses?

a. Benefit-cost ratio
b. Present value
c. Future value
d. Payback period

A

A. The benefit-cost ratio compares the benefit or revenue of a project with the cost of or investment in a project.

36
Q

Your project team has just completed the first phase of a project. Prior to initiating the next phase, you send the client a batch sample of the finished product and receive feedback that some changes will be necessary. This is an example of which project life cycle?

a. Adaptive
b. Iterative and incremental
c. Directive
d. Predictive

A

A. Adaptive life cycles request customer review and feedback following completion of each project phase. One of the key benefits of an adaptive life cycle is the ability to make changes early during each phase of the project, keeping scrap and rework to a minimum.

37
Q

Which of these is NOT part of a benefits management plan?

a. Strategic alignment
b. Timeframe for realizing benefits
c. Target benefits
d. Objectives and reasons for the project

A

D. A benefits management plan will contain strategic alignment, the timeframe for realizing benefits, and the target benefits. The objectives and reasons for the project are part of the business case

38
Q

If an organization were to focus on the amount of money being spent recruiting and training new hires, which of the following nonfinancial metrics might be most useful?

a. Public opinion
b. Future opportunities
c. Employee retention
d. Customer satisfaction

A

C. The process of maintaining employees (or employee retention) is a common nonfinancial metric that organizations consider

39
Q

Defining activities, sequencing activities, and estimating durations are all included as Project ________ Management processes.

a. Scope
b. Schedule
c. Cost
d. Quality

A

B. Project Schedule Management includes the processes required to manage the timely completion of a project.

40
Q

Which of the following terms are typically used to define a project?

a. Lengthy and expensive
b. Temporary and similar
c. Temporary and unique
d. Permanent and costly

A

The best answer choice is C because a project is typically defined by the terms temporary and unique.

41
Q
navigate.Sequence Activities, which is the process of identifying and documenting relationships among project activities, is part of the \_\_\_\_\_\_\_\_\_\_\_\_\_\_ process group and the Project \_\_\_\_\_\_\_\_\_\_\_\_\_\_ Management knowledge area.
Planning, Stakeholder
Executing, Procurement
Planning, Schedule
Planning, Resources
A

C. Sequence Activities is part of the Planning process group, the details of which are found within the Project Schedule Management knowledge area.

42
Q

A financial assessment that determines how soon you can expect to recapture your investment and start making a profit is called:

a. Cost-benefit analysis
b. Payback period
c. Net present value
d. Sunk costs

A

B. By definition, the payback period calculates the initial investment and the estimated income over time to determine when you will recapture your investment

43
Q

The Project Management Knowledge Areas include which of the following?

a. Cost management
b. Initiating
c. Executing
d. Planning

A

The best answer choice is A because it is the only option that represents a knowledge area. The other options are process groups.

44
Q

You are tasked with completely updating your organization’s communication infrastructure. You decide to break this into several components: one each for telephones, IT, and radio communication. Each will have its own manager. This is an example of

a. A project
b. A portfolio
c. A program
d. Operations

A

C. This is a program. Each component is a project

45
Q

Which of the following is NOT one of the PMI-identified competing constraints?

a. Market conditions
b. Quality
c. Schedule
d. Resources

A

A. Market conditions might be an enterprise environmental factor, but they’re not one of the competing constraints.

46
Q

The types of project life cycles are predictive, incremental, adaptive, and ___________?

a. Controlling
b. Administrative
c. Supportive
d. Iterative

A

D. The types of project life cycles are predictive, incremental, adaptive, and iterative

47
Q

When comparing the reward or income of a project to the project’s expenses, which of the following metrics would be most useful?

a. Cost/benefit ratio
b. Net present value
c. Payback period
d. Future value

A

A. The cost/benefit ratio compares the benefit or revenue of a project with the cost of (or investment in) a project.

48
Q

You are planning a small renovation project. What should be one of the first tasks you undertake?

a. Identifying the competing constraints of the project
b. Starting the contracting process for the work you’ll outsource
c. Publishing the schedule
d. Hiring the necessary resources

A

A. Your primary function as project manager is to plan the project around the competing constraints, communicate them, and manage the project accordingly during execution of the work.

49
Q

You work for a commercial roofing contractor. You are asked to do a job in Barrow, Alaska. Which EEF do you need to pay closest attention to?

a. Company culture
b. Infrastructure
c. Weather
d. Availability of resources

A

C. In Alaska, weather is always an EEF

50
Q

Organizations that are concerned with workflows that are costly or ineffective will focus on which of the following nonfinancial metrics?

a. Customer retention
b. Employee satisfaction
c. Process improvement
d. Future opportunities

A

C. Process improvement, or the act of increasing the efficiency of organizational procedures, is a common nonfinancial metric that organizations consider.

51
Q

You are assigned an endeavor with many large deliverables to manage and coordinate. After some consideration, you decide to break the effort down into several components, each with its own manager. This is an example of:

a. Project management
b. Program management
c. Portfolio management
d. Operations management

A

B. The definition of a program is a group of related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.

52
Q

You are planning a small construction project. What will be one of your first tasks?

a. Identify your suppliers
b. Hire the necessary personnel
c. Identify the competing constraints
d. Prepare a schedule

A

C. Part of your job as a project manager is to first identify the competing constraints and then manage your project to balance them appropriately.

53
Q

A customer for a large software rollout has requested that you complete your project earlier than planned. Which constraints on the project will need to be evaluated if this request is to be approved?

a. Scope, quality, and costs
b. Resources, contracts, and quality
c. Integration, stakeholder buy-in, and senior management approval
d. Communications, schedule, and resources

A

A. A shortened schedule typically affects scope, quality, and costs. Additionally, there are often increased risks when attempting to do so.

54
Q

Which of the following is NOT an example of an organizational process asset?

a. Templates
b. Lessons learned from previously completed projects
c. A change management process
d. Risk tolerance

A

D. Risk tolerance is an example of an enterprise environmental factor (EEF).

55
Q

navigate. Tektron Industries produces irrigation systems for small farms. Over the last financial quarter, the company noted an increase in requests for collapsible hoses that would lie flat when not in use. The company surveyed its regular customers and 85% of the respondents said they are considering replacing their current irrigation system with one that uses collapsible hoses. Tektron Industries recently initiated a project for developing and manufacturing collapsible hoses. This would be an example of which reason for initiating a project according to the PMBOK® Guide?
a. Market demand
b. Business need
c. Legal requirement
d. Social need

A

A. Tektron Industries is initiating a project to develop a new product based on the demands of their market.

56
Q
Validate Scope, which is the process of formalizing acceptance of the completed project deliverables, is part of which process group and which knowledge area?
Planning; Schedule
Planning; Scope
Monitoring and Controlling; Scope
Monitoring and Controlling; Procurement
A

C. Validate Scope is a Monitoring and Controlling process and is part of the Scope knowledge area.

57
Q

What is one advantage of a functional organization structure?

a. Timely responses to changes
b. Team members report to one manager
c. Rapid reaction to changes
d. Flexible resource scheduling

A

D. Advantages of a functional organization structure include a broad specialist base, shared knowledge of latest technology, and flexible resource scheduling.

58
Q

Which of the following is not considered a project management process group?

a. Planning
b. Integration
c. Initiating
d. Executing

A

B. The best answer choice is B. The five process groups include Initiating, Planning, Executing, Monitoring and Controlling, and Closing. Project Integration Management is a knowledge area.

59
Q

navigate. What is an output?
a. A systematic series of activities directed toward causing an end result
b. A product, result, or service generated by a process, which may be an input to a successor process
c. A defined systematic procedure to perform an activity to product a product, service, or result
d. Something tangible used in performing an activity to produce a product or result

A

B. The PMBOK® Guide definition of an output is a product, result, or service generated by a process, which may be an input to a successor process.

60
Q

Which of the following best defines a sunk cost?

a. A cost that has already been incurred and cannot be recovered
b. A cost that has already been incurred but can be recovered
c. A cost that has been incurred by selecting one project over another
d. A cost that has not yet been incurred by selecting one project over another

A

A. A sunk cost is money that an organization has already spent and, because it can’t get it back, should not be factored into future expenditures.

61
Q

Sponge-Back Technologies services their market with shock-absorbent packaging. Over the past year, the company has noticed an increase in demand for most of their packaging products, along with frequent requests for custom cutout configurations. The company has decided to invest more than $65,000 on a specialized machine that will slice block sponges into any desired shape or size requested by a customer. Which of the following project initiators best describes this situation, according to the PMBOK® Guide?

a. Organizational need
b. Legal requirement
c. Social need
d. Market demand

A

D. A project is being initiated because of a market demand opportunity available to Sponge-Back Technologies

62
Q

The four types of project life cycles are predictive, ________, incremental, and adaptive.

a. Supportive
b. Controlling
c. Iterative
d. Directive

A

C. The four types of life cycles are predictive, iterative, incremental and adaptive

63
Q

The standards, codes, and regulations that a company operates under are all examples of:

a. Enterprise environmental factors
b. Company culture
c. Ethics policies
d. Professional conduct policies

A

a The PMBOK® Guide states that enterprise environmental factors are conditions that are not under the immediate control of the team and that influence, constrain, or direct the project, program, or portfolio

64
Q

Sponge-Back Technologies services their market with shock-absorbent packaging. Over the past year, the company has noticed an increase in demand for most of their packaging products, along with frequent requests for custom cutout configurations. The company has decided to invest more than $65,000 on a specialized machine that will slice block sponges into any desired shape or size requested by a customer. Which of the following project initiators best describes this situation, according to the PMBOK® Guide?

a. Organizational need
b. Legal requirement
c. Social need
d. Market demand

A

D

65
Q

In which of the following documents are all of the subsidiary plans and baselines contained?

a. Project scope statement
b. Project management plan
c. WBS dictionary
d. Statement of Work

A

B

66
Q

Which of the following metrics takes the present value and deducts the costs of upfront and ongoing expenditures?

a. Future value
b. Net Present Value
c. Payback value
d. Benefit-cost value

A

B

67
Q

When choosing between two or more mutually exclusive alternatives, which project cost evaluation would be appropriate?

a. Incurred cost
b. Sunk cost
c. Recoverable cost
d. Opportunity cost

A

D

68
Q

A schedule has deliverable milestones defined for only the first three months of the project. The project manager intends to provide a more detailed schedule as the work progresses, following a more thorough understanding of the project. This approach to project planning is called:

a. Planning
b. Life cycling
c. Progressive elaboration
d. Requirements evaluation

A

C