Integration Management Processes Flashcards

1
Q

Document prepared in the initiation phase that formally authorizes the project to exist.

A

Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In this process, a document is prepared and given to the authoritative project manager to use the resources required for the project.

A

Develop Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Process of combining all the project plans and sub-plans into a single integrated plan.

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In this process, the project work activities are directed and managed while executing.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The key outputs of this process are final deliverables and change requests for the project work.

A

Direct and Manage Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The main objective of this process is to improve the project process using the existing knowledge and creating new knowledge.

A

Manage Project Knowledge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Continuous tracking, reviewing and reporting the project progress status to achieve the required target of the project work activities.

A

Monitor and Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A document is prepared regarding the issue and the improvement possible.

A

Monitor and Control Project Work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reviewing all the change requests and managing them effectively from all the working departments.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A document is prepared for approval of any change requests.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Change requests are approved when there is not much impact on scope, time and cost of the project.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Change requests are project deliverables, a project plan or project assets.

A

Perform Integrated Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Finalizing all the deliverables of project activities and the documents related to closing the project or phase.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Resources are released to work for other projects.

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

List all the processes of Integration Management

A
Develop Project Charter
Project Management Plan
Direct and Manage Project Work
Manage Project Knowledge
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase (7)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is integration management?

A

Coordinating resources, stakeholders, and other project elements to ensure successful execution of the project end to end.

17
Q

The only knowledge area that has at least one process win every process group.

A

Project Integration Management

18
Q

Which two processes in Integration Management must you do in order?

A

Develop project charter and close project