Integration Management Flashcards

1
Q

Develop Project Charter

A

The process of developing a document that formally authorizes a project or phase and documenting initial requirements that satisfy the stakeholder’s needs and expectations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Management Plan

A

The process of documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans. The PM plan becomes the primary source of information for how the project will be planned, executed, monitored & controlled, and closed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Direct and Manage Project Execution

A

The process of performing the work defined in the project management plan to achieve the project’s objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Monitor and Control Project Work

A

The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan. Monitoring includes status reporting, progress measurement, & forecasting. Performance reports provide information on the proj’s performance with regard to scope, schedule, cost, resources, quality & risk, which can be used as inputs to other processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Perform Integrated Change Control

A

The process of reviewing all change requests, approving changes, and managing changes to 1. the deliverables, 2. organizational process assets, 3. project documents, & 4. the project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Close Project or Phase

A

The process of finalizing all activities across all of the project mgmt PGs to formally complete the project or phase (by getting the final acceptance / sign-off from the customer).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly