Integration Flashcards

1
Q

Develop Project Charter – Inputs:

A

“1. Business Documents
* Business Case
* Benefits management plan
2. Agreements
3. Enterprise environmental factors
4. Organizational process assets”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Develop Project Charter –Tools:

A

“1. Expert Judgement
2. Data Gathering
* Brainstorming
* Focus Groups
* Interviews
3. Interpersonal & Team Skills
* Conflict Management
* Facilitation
* Meeting Management
4. Meetings”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Develop Project Charter –Outputs

A

“1. Project charter
2. Assumption Log”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Develop Project Management Plan – Inputs

A

“1. Project Charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organizational process assets”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Develop Project Management Plan – Tools

A

“1. Expert Judgement
2. Data Gathering
* Brainstorming
* Checklists
* Focus Groups
* Interviews
3. Interpersonal & Team Skills
* Conflict Management
* Facilitation
* Meeting Management
4. Meetings”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Develop Project Management Plan –Outputs

A
  1. Project management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Direct and Manage Project Work –Inputs

A

“1. Project management plan
* Any component
2. Project documents
* Change Log
* Lessons Learnt Register
* Milestone List
* Project Communications
* Project Schedule
* RTM Requirements Tracebility Matrix
* Risk Register
* Risk Report
3. Approved change requests
4. Enterprise environmental factors
5. Organizational process assets”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Direct and Manage Project – Tools

A

“1. Expert Judgement
2. Project management information system (PMIS)
3. Meetings”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Direct and Manage Project – Outputs

A

“1. Deliverables
2. Work performance data
3. Issue Log
4. Change requests
5. Project management plan updates
* Any component
6. Project document updates
* Activity List
* Assumption Log
* Lessons Learnt Register
* Requirements Documentation
* Risk Register
* Stakeholder Register
7. Organization Process Assets updates”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Manage Project Knowledge – Inputs

A

“1. Project management plan
* Any component
2. Project documents
* Lessons Learnt Register
* Project team assignments
* RBS Resource Breakdown structure
* Source selection criteria
* Stakeholder Register

  1. Deliverables
  2. Enterprise environmental factors
  3. Organizational process assets”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Manage Project Knowledge – Tools

A

“1. Expert Judgement
2. Knowledge management
3. Information management
4. Interpersonal & Team skills
* Active Listening
* Facilitation
* Leadership
* Networking
* Political awareness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Manage Project Knowledge – Outputs

A

“1. Lessons Learnt Register
2. Project management plan updates
* Any component
3. Organization Process Assets updates”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Monitor and Control Project Work – Inputs

A

“1. Project management plan
* Any component
2. Project documents
* Assumption Log
* Basis of estimates
* Cost forecasts
* Issue Log
* Lessons Learnt Register
* Milestone Lists
* Quality report
* Risk register
* Risk reports
* Schedule forecasts

  1. Work Performance Information
  2. Agreements
  3. Enterprise environmental factors
  4. Organizational process assets”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Monitor and Control Project – Tools

A

“1. Expert Judgement
2. Data Analysis
* Alternative Analysis
* Cost-Benefit Analysis
* Earned Value Analysis
* Root Cause Analysis
* Trend Analysis
* Variance Analysis
3. Decision Making
4. Meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Monitor and Control Project – Outputs

A

“1. Work Performance Reports
2. Change requests
3. Project Plan updates
* Any component
4. Project document Updates
* Cost forecasts
* Issue Log
* Lessons Learnt Register
* Risk register
* Schedule forecasts”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Perform Integrated Change Control — Inputs

A

“1. Project management plan
* Any component
2. Project documents
* Assumption Log
* Basis of estimates
* Cost forecasts
* Issue Log
* Lessons Learnt Register
* Milestone Lists
* Quality report
* Risk register
* Risk reports
* Schedule forecasts

  1. Work Performance Information
  2. Agreements
  3. Enterprise environmental factors
  4. Organizational process assets”
17
Q

Perform Integrated Change Control – Tools

A

“1. Expert Judgement
2. Data Analysis
* Document Analysis
* Regression Analysis
* Trend Analysis
* Variance Analysis
3. Meetings

18
Q

Perform Integrated Change Control – Outputs

A

“1. Approved change requests
2.Project management plan updates
* Any component
3. Project document updates
* Change Log”

19
Q

Close Project or Phase – Inputs

A

“1. Project Charter
2. Project management plan
* All components
3. Project documents
* Assumption Log
* Basis of estimates
* Change Log
* Issue Log
* Lessons Learnt Register
* Milestone Lists
* Project Communications
* Quality control measurements
* Quality reports
* Requirements Documentation
* Risk Register
* Risk reports
4. Accepted Deliverables
5. Business Documents
* Business Case
* Benefits management plan
6. Agreements
7. Procurement documentation
8. Organizational process assets”

20
Q

Close Project or Phase – Tools

A

“1. Expert Judgement
2. Data Analysis
* Document Analysis
* Regression Analysis
* Trend Analysis
* Variance Analysis
3. Meetings

21
Q

Close Project or Phase – Outputs

A

“1. Project document updates
* Lessons learnt register
2. Final product, service or result transition
3. Final report
4. Organizational process assets updates”