Instructing.org Flashcards
Cost Management
What is Actual cost (AC)?
AC is key component in Earned Value Management
The actual amount of monies the project has spent to date.
Cost Management
What is Analogous estimating?
An approach that relies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.
Cost Management
What is Bottom-up estimating?
An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs.
Cost Management
What is Budget estimate?
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
Cost Management
Commercial database
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Cost Management
What is Contingency reserve?
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
Cost Management
What is Cost aggregation?
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
Cost Management
What is Cost baseline?
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.
Cost Management
What is Cost budgeting?
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
Cost Management
What is the Cost change control system?
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
Cost Management
What’s the purpose of a Cost management plan?
The cost management plan dictates how cost variances will be managed
Cost Management
What is Cost of poor quality?
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.
Cost Management
What is Cost of quality?
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
Cost Management
What does Cost performance index (CPI) do?
Measures the project based on its financial performance.
The formula is CPI = EV/AC.
Cost Management
What is Cost variance (CV)?
The difference of the earned value amount and the cumulative actual costs of the project.
The formula is CV = EV – AC.
Cost Management
What are Definitive estimate?
- This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating.
- You need the WBS in order to create the definitive estimate.
- The range of variance for the estimate can be from –5 percent to +10 percent.
Cost Management
What are Direct costs?
Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on).
Cost Management
What is Earned value (EV)?
Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
Cost Management
What is Estimate at completion (EAC)?
These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project.
Cost Management
What is Estimate to complete (ETC)?
An earned value management formula that predicts how much funding the project will require to be completed. Three variations of this formula are based on conditions the project may be experiencing.
Cost Management
What are Fixed costs?
Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).
Cost Management
What is Funding limit reconciliation?
An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints
Cost Management
What are Indirect costs?
Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project management software license, and so on).
Cost Management
What are Known unknown?
An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.
Cost Management
What is the Learning curve?
An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.
Cost Management
Oligopoly
A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.
Cost Management
Opportunity cost
The total cost of the opportunity that is refused to realize an opposing opportunity.
Cost Management
Parametric estimating
An approach using a parametric model to extrapolate what costs will be needed for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.
Cost Management
Planned value (PV)
Planned value is the work scheduled and the budget authorized to accomplish that work. It is the percentage of the BAC that reflects where the project should be at this point in time.