incorrect question concepts Flashcards
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Cost management plan
What is a regression line used to estimate?
How a change to the independent variable influences the value of the dependent variable.
Which is the appropriate tool to identify the possible correlation between two elements in a process?
A scatter diagram
Is a change control system defined in a contract?
no
Quality planning is more important than…
inspection and prevention
Is the cost of quality of a product higher in the production stage or planning stage?
production
What is contingency planning in quality?
There is no such theory as contingency planning in quality management.
Can a project have more than one critical path?
yes
Which Control Quality tool is also known as an arrow diagram?
Activity Network diagram
What chart shows show loops and branches?
Gantt chart
What do resource requirements specify?
the quantity and type of resources required in a work package.
What is a schedule compression technique employed to shorten the project duration for the least amount of incremental cost by adding resources for an activity on the project’s critical path.
Crashing
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
Perform Integrated Change Control
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Activity attributes
How can a project manager evaluate project team development?
Produce team performance assessments
The project manager is dividing the project scope into smaller pieces, and repeating this process until no more subdivisions are required. At this point the project manager is able to estimate costs and activities for each element.
What are these elements called?
work packages
Which key benefit can a project manager obtain by identifying stakeholders?
Identify the appropriate focus for engagement of each stakeholder
What is the most inclusive in a project environment hierarchy
Portfolios
Two members of the team are having a conflict. The project manager decides that, in this case, the best solution is to bring some degree of satisfaction to all parties in order to temporarily or partially resolve the problem.
Which technique should the project manager use?
Smooth and accomodate