Formulas Flashcards
PERT
Aka beta distribution or weighted average
O+(4 x R)+P/6 = PERT
Standard Deviation
P - O/6
Cost Variance
CV = EV - AC
Schedule Variance
SV = EV - PV
Cost Performance Index
CPI = EV / AC
Schedule Performance Index
SPI = EV/PV
Estimate at Completion
EAC = Budget at Completion/CPI
Estimate to Complete
ETC = EAC - AC
Variance at Completion
VAC = BAC - EAC
To Complete Performance Index
TCPI = ( BAC- EV)/(BAC - AC)
Present Value Formula
PV = FV/(1+R)n
Communication Channels
N(N-1)/2
Expected Monetary Value
EMV = Probability / MV of impact
Point of Total Assumption
PTA = ((Ceiling Price - Target Price)/Buyers Share) +Target Cost
Future Value
FV = PV x (1+R)n
Net Present Value
(CF1/(1+r)) x (CF2/(1+r)) - Investment
Early Finish
Early finish/EF = earliest start + duration – 1
Late Start
Late Start/LS = LF – duration + 1.
Standard depreciation
(cost of assets – scrap value)/useful life
BAC
BAC = estimated cost + contingency reserves + management reserves.
Planned Value
PV = % of work completed x BAC
Earned Value
EV = % of work completed x BAC
Expected Present Value
EPV = Probability of PV x PV
Rolled Throughput yield
RTY = Y1 x Y2 x Y3 x….
Activity duration
Work = duration/days x units/hours
Safety margin
1/2 way between average and worst
Ceiling Price
Ceiling Price is: (Target Cost + Buyer’s Share of the cost overruns + Seller’s Target Profit or Fixed Fee).
Target Price
Target Price will be: (Target Cost + Seller’s Target Profit or Fixed Fee)
Cost Overrun
Cost Overrun = Actual Cost – Target Cost
Buyer’s share of cost overrun
Buyer’s share of Cost overrun = Buyer’s ratio x cost overrun
Seller’s share of cost overrun
Seller’s share of Cost overrun = seller’s ratio x cost overrun
Payback period
Investment / periodic cash flow
Finding slack for a single activity not on the critical path
Critical path days – activity path days = slack for the activity.
Return on Investment
ROI = Financial value - project cost / project cost x 100
Total Float
Using any activity not on the critical path. Late finish date - Early finish date
OR
Sum of critical path days - sum of non critical path days
Free float
For a single task: ES of the successor activity - EF of the current activity - 1
burn rate
Actual Cost/ Earned Value
Probability of occurrence
Prob of Oc = # of favorable events that can occur / # of total events that can occur
triangular distribution in 3 point estimating
Aka simple averages.
= O+P+R / 6
Throughput yield
of quality products / total # of products