Hinze - Chapters 1 - 4 Flashcards
What is the role of the owner, designer, and contractor and do they need to be three separate parties?
Owner: determines when a particular project is needed
Designer: create guiding documents for the contractor
Contractor: builds the project
Do not need to be three separate parties
What are the 5 types of contracting procedures in the construction industry and do pure forms of each exist?
Often modified by owners, pure forms do exist for each type
General Contract Method, Separate Contracts Method, Self Performance Method, Design-Build Method, Professional Construction Management Method and, Construction Management at Risk
What is a General Contract Method
Often referred to as design-bid-build.
The contract between an owner (represented by the design firm) and a contractor.
Which method gives the owner a confirmed cost (rather than an estimate)?
General Contract Method
What are the main benefits of a General Contract method?
Owner gets a confirmed cost, rather than an estimate.
GC provides construction management skills which the owner may not have.
What are some downsides to the General Contract method?
Extends project timelines
Tight bids and small profit margins
Creates bad relationships (due to the bidding and award structure)
What is a Separate Contracts Method
Also known as multiple prime contracts method. The owner acts as GC and has separate contracts with each subcontracter
When is a Separate Contracts Method adviseable
Separate contract method is advisable if the personale are available and the work is restricted to a few types of construction
What are the potential downsides to a Separate Contracts Method
Delays can occur if the permit is not acquired for projects in the private sector, most places will require a GC license
The owner assumes more risk.
What is the Self-Performance Method and when is it appropriate?
In a Self-Performance Method the owner may self-perform (complete in-house) work, also known as force account work.
Appropriate when project is small in scope, simple in character and ongoing in nature, common to maintenance works.
What is the Design-Build Method?
Also known as design-construct or turnkey construction. The owner lets a single contract for the design and the construction of the project
When is the Design-Build Method advisable?
Advisable when projects are large and technically complex
What is the Professional Construction Management Method?
Owner hires a firm to provide construction management (CM) services on their behalf
What is the Construction Management at Risk?
Not setting up the CM as an agent of the owner (as with Profession Construction Management Method) the CM is an independent contractor and so is responsible to complete the project by the established completion date and within the budget
What conditions must exist for the Separate Contracts Method to be viable
owner must have necessary in-house capabilities to manage the project i.e. a competent construction manager or construction engineer to administer the contracts
What are the criticisms of self-performance or force account work?
Unfair in the bidding process, not held to the same wage laws that construction companies are held to.
What type of construction is well suited for force account work
Force account (or self-performance method) is particularly appropriate for small scope projects that are simple and ongoing in nature
What type of project might be ideally suited for the design-build or design-construct method?
large industrial-type projects
What are the advantages to using the professional construction management approach?
provides flexibility to change the project as the design evolves
Which types of contractual arrangements lend themselves to fast-tracking?
find the answer
Describe how different contracting approaches differ in terms of allocating risk.
find the answer
What is the definition of a contract?
An agreement between two parties enforceable by law