Hinze Chapter 11-14 Flashcards
Balanced bid
a bid which the anticipated costs for the various items are accurately reflected in the unit prices that are submitted
Unbalancing a bid
is a method used by some contractors in which the unit prices of the various bid items are altered so they do not reflect the true cost of the item
Can an owner reject an unbalanced bid?
Can be rejected as being irregular
What are the disadvantages of a unit price contract?
Owner won’t be certain of actual cost until the project is complete. The extent of this shortcoming is directly related to the accuracy of the estimate
When is an unit price contract appropriate?
Unit price contracts are appropriate for when the project is well defined but the actual quantities are impossible to estimate with accuracy until after construction has started
Cost-Plus Contract
A contractor is reimbursed for most of the direct expenditures associated with a particular project plus an allowance for overhead and profit. Can be used with a guaranteed maximum. Savings in this case can be shared between the owner and the contractor
When is a cost-plus contract appropriate?
This contract is appropriate when the actual costs of the project are difficult to measure with accuracy. This could be due to incomplete plans, the project cannot be accurately portrayed or if a short time period. Can be useful if a lot of changes are anticipated throughout the project.
What categories of reimbursements are there in a cost-plus contractor
Contractor’s reimbursement will fall into the categories of Labour, Materials and Equipment, and subcontractor costs
Lump Sum Contract
- Most common type of contract used in the construction industry
- On most of these contracts the contractor will be made out monthly
- Value of ind. Items is ideally set out before the start of construction
Job Order Contracting (JOC)
- An ‘on call’ contractor for work relating to renovation, repair and construction projects
- Ensures quick contractor response for work that arises without notice
Cardinal Changes
Changes not within the general scope
What are the risks to a contractor who performs work required by a cardinal change
May not be able to force payment
What are the risks to the owner’s rep in authorizing a cardinal change?
Forcing the contractor to do this change would be a breach of contract
It is common for contracts to stipulate that changes in the work be authorized in writing by someone in authority. Under what conditions might a verbal change be considered valid?
If the new work initiated a new contract or in the case of emergency situations
When does the owner has an inherent or implied right to make reasonable changes to the project
Changes within the general scope of the project