HIGH-RISE TM Flashcards
What is the main responsibility of the SP Control position?
pressure control on inline gauge
When might rooftop SP connections be used for FA?
minor fires involving rooftop equipment such as mechanical rooms or penthouses
NFPA 14 requires buildings constructed before 1993 ___ min residual pressure at ___. post 1993? 1993?
65 psi, highest standpipe outlet
100 psi
beats me
when must PRVs or PRDs be used?
when standpipe system pressure exceeds maximum allowable limit, usually 175 psi
What type of PRDs are usually threaded onto an outlet and easily removable?
orifice plates and mechanical devices
What are the 3 types of PRDs?
orifice plates, mechanical devices, valve restrictors
____ are usually removable or adjustable with a screw-driver and this is a recommended practice for field ops.
valve restrictors
some new types of ____ are fireground adjustable (adjustable with valve open and flowing water).
PRVs
what step critical when setting up for a stairwell stretch due to poor conditions on fire floor?
deploying SP pack in hallway below fire floor so officer can get idea of layout and necessary hose length
which side of door should nozzle be on for hallway stretch? stairwell?
hinge
lock
the first step of any high-rise water supply operation is ___. the next step is __.
finding the FDC
spotting apparatus close enough to deploy 3” to FDC
what type is recommended for an aerial blitz?
solid or straight
if a building has separate FDCs for different sections of the building, when should you consider supplying both sections?
location of fire is in doubt
What should be done if the building has separate FDCs which require different pressures? And requires tandem pumping?
use a second engine
tandem: engine at hydrant can be used to supply the lower pressure FDC
where in CAD incident notes can you find required system pressure?
premise hazard section
when should 3” hose being used to supply the FDC be secured and protected?
when system pressure is above 225 psi
TM recommends one method for keeping pump cool in standard water supply, and a different method for tandem pumping supply ops. what are they?
Standard: crack tank-fill
Tandem: flow water through booster or bumper
what is the preferred method and first choice of starting an electric fire pump?
put the pump control level in MANUAL position
At a high-rise, personnel assigned to check the operational readiness of the pump should report their findings to ___. What about at a Mid-rise?
Command
Mid-Rise is WSGS
Both Mid/High: notify Command if pump doesn’t start, or in any event of valve closure
Lobby Control should send the bldg engineer to ___, and bldg manager to ___.
engineer to FCR
manager to CP
which radio channel should Lobby Control Officer monitor?
primary firetac, for direction from Logistics to switch to alternate
*if possible, get 2nd radio to monitor Direct16, or have FF monitor.