if top is flow what must bottom boundray be
stage hydrograph of tide to restrain water levels
other boundry conditions for water
rating curve
time series of gate openings
what is a rating curve
discharge vs stage
boundary conditions for sediment transport
bed gradation
load equilibrium
rating curve (sed load to load)`
what three changes d you want to get cross sections at
geometry changes
hydraulic structures
flow changes
four modelling types
flood waves-DAMBRK
water quality-QUAL2e
water profile-Hec_RAS
habitat modelling _PHABSIM
two eautions and the assumnptions for HEC RAS in findinw ater profile
cons mass
cons momentum
incompressibke
boittom slope small
flow parralle to bottom slope
what are 6 reasons why it will be unstable
1 large changes in water levels 2. large time step with different n's 3 bad Bc's (two flows) 4 incomplete geometry 5 transition sub super sub 6 hydraulic structures too small
how many dimensions for hec
1d
name of equation it is based on
st venant
2 indepedatn and 2 dependent
inde- x and t
dep
Q and h
example of steady
quasi steady
and unsteady
steady-flood plain management
quasi steady- sedimet
transient-model storage, seasonl changes