What is the maximum width of a trench before a bridge is required ?
30”
What is the maximum DEPTH of a trench before a bridge is required ?
6’
You have encountered asbestos while working on site with a HAZWOPER training person, what should you do ?
contact DOSH for directions
What action should be taken prior to the transportation of a removed UST?
provide a vent hole in a tank plug
If a respirator has been contaminated and must be thrown out, what kind of waste is it considered to be ?
Hazardous waste
What is the first thing a contractor should do once his bid has been accepted for a hazardous waste removal project ?
Contact the local regulatory agencies
Why is pea gravel a preferred fill?
It does not need to be compacted
How long must a hazmat site be open before you need a shower station ?
6 months
How is radioactive waste classified ?
Mixed waste
When is a shipping manifest required for transporting hazardous material ?
A. Shipment by rail
B. Shipment by water
C. Shipment by roadway
D. Always
C. Shipment by roadway
How is pea gravel backfill protected from infiltration of fines ?
Install filter fabric between the pea gravel and soil
Which of the following is NOT recommended backfill material for steel UST installations?
A. Topsoil
B. Sand
C. Crushed Rock
D. Pea Gravel
A. Topsoil
Which of the following is NOT a recommended backfill material for nonmetallic UST installations ?
A. Peagravel
B. Crushed rock
C. Crushed gravel
D. Sand
D. Sand
When using pea gravel as backfill material for steel or nonmetallic UST installations, the largest particle should be no more than ____ in diameter .
3/4”
When using crushed rock for backfill material, the largest particle should not be more than ___ in diameter .
1/2”
What hazards apply to the removal of above-ground oil storage tanks ?
Benzene, asbestos, explosions, lead
What should the operator do if the sling for lifting a tank is found to be too horizontal to the tank top ?
Use a spreader beam
A countercurrent packed tower is used in air stripping to remove:
Volatile organic components from aqueous waste
A major disadvantage of a countercurrent packed tower is:
It has high energy cost
Gasoline vapors are lighter or heavier than air?
Heavier
During UST removal, keep the tank vented at least ___ above ground.
12 feet
During excavation for installation or removal of a UST, maintain at least ___ from the edge of the excavation to the bottom of an adjacent building foundation.
5 feet
When excavating to remove a UST, a public barricade should be erected at least _____ from the edge of the excavation.
50 feet
When excavating to remove a UST, allow at least ____ at the side and ends to leave room for a one-yard bucket.
3 feet