Hannes Marais S2 Flashcards
1
Q
What are the different Construction Procurement Strategies?
A
Design build - (contractor designs and builds the development)
Design, Build, operate, maintain
BOT - build, operate, transfer
BOOT - build, own, operate, transfer
DBFM - design, build, finance and maintain
2
Q
What factors will influence choice of strategy?
A
◦Nature of the project ◦Project Size ◦Time pressure ◦Knowledge at the time of procurement ◦Need to know final cost ◦Project schedule - time constraints
3
Q
Commonly used pricing strategies in construction procurement?
A
◦Lump Sum Contract
◦Re-measurable Contract (Bill of Quantities)
◦Cost reimbursable Contract (Schedule of Rate)
4
Q
Sketch project life cycle.
A
SEE SLIDE 5
5
Q
Sketch project life cycle budgeting.
A
SEE SLIDE 6
6
Q
What is the basic principles to a tender process?
A
- Invitation to make an offer
- Offer is based on information provided
- Tender information to be complete
- Essential principle: same information made available to all tenderers
- Strict tender rules to apply
7
Q
What is the required tender documents for the tender process?
A
- Notice to tenderers
- Conditions of tender (tender rules)
- Tender Form
- Schedule of information to be provided by tenderers
- Conditions of Contract
- Scope of the Works (drawings, specifications)
- Special conditions and specifications
- Bill of Quantities (prices)
- Site Information (sub-soil conditions)