H&S Test 2 Flashcards

1
Q

CDM Regulation 2 defines “construction work” as…

A

The carrying out of any building, civil engineering or engineering construction work (with list of inclusions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Two specific phases of projects under CDM are…

A

1) Pre-construction phase

2) Construction phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Four key CDM documents are…

A

1) F10 Document
2) PCI - Pre Construction Info
3) CPP - Construction Phase Plan
4) H&SF - Health & Safety File

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Three key parties to a project under CDM…

A

1) Client
2) Principal designer
3) Principal contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

True or false;

There can be only one entity to each key duty holder position i.e. client, PD, PC)

A

True;

While there may be more than one client, designer and or contractor one entity should be nominated to hold each key position for the purposes of CDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Filing of F10 document is the responsibility of…

A

The client (or their appointed specialist to carry out on their behalf)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Compiling PCI is carried out by…

A

Combination of client and principal designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPP is produced by

A

Principal contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

H&SF is compiled by….

A

Either the principal designer or principal contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

F10 document is used to…

A

Inform HSE of any projects which are over 500 person days in duration or have a duration of over 30 days with over 20 operatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Examples of info within the PCI are (5);

A

1) Planning and design info
2) Client requirements
3) Survey results
4) Details of any existing hazards
5) Details of any hazards within the design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The CPP contains items such as (4) and is used to manage the site safely

A

1) H&S site management policies and procedures
2) Site rules
3) Site controls
4) Site welfare details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The H&SF is issued to the ____________ upon completion of the works and provides details such as (4)

A

Client / end user

1) O&M info
2) Details of residual hazards
3) H&S info relevant to future works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

True or false;

One entity can occupy more than one key duty holder position;

A

True;

The principal designer and principal contractor can be the same entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Key CDM acronym;

SKE

Stands for…

A

Skills, knowledge and experience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Key CDM acronym

ERIC

Stands for…

A

Eliminate, reduce, inform & control

17
Q

Key CDM acronym

PMMC

Stands for…

A

plan, manage, monitor & co-ordinate

19
Q

Why is it important for the client to make their appointments of PD and PC in writing…

A

If they do not do this then they assume the roles and responsibilities of the PD and PC

20
Q

Key CDM acronym

SKET

Stands for…

A

Skills, knowledge, experience & training

23
Q

There are five general duties which are applicable to all parties, these are;

A

1) SKE - all operatives have a duty to ensure they have the correct SKE for the job they are carrying out - all management have a duty to ensure their operatives have the correct SKE
2) Duty to ensure they have the organisational capability to carry out the works and ensure their subs have the same i.e. H&S procedures and policies etc.
3) Duty to report and H&S issues, incidents, accidents
4) Duty to provide comprehensible info
5) Duty to co-operate

24
Q

“5 Pillars” of duty holders on projects are;

A

1) Client
2) PD
3) Designers
4) PC
5) Contractors

25
Q

Some clients duties under CDM (3);

A

1) Appoint PD & PC in writing
2) Help to provide PCI
3) Ensure all parties are operating correctly under CDM

26
Q

Some PD duties under CDM are (6);

A

1) Ensure client knows CDM duties
2) Compile PCI
3) Apply principles of prevention to design (ERIC)
4) Ensure all designers have followed correct process
5) Liaise with PC
6) H&SF (if applicable)

27
Q

Some duties of designer under CDM (3);

A

1) Ensure client knows CDM duties
2) Apply principles of ERIC
3) Responsible for CDM of non GB contractors

28
Q

Some duties of PC under CDM (6);

A

1) PPMC
2) ERIC
3) Compile CPP and implement
4) Compile H&SF (if applicable)
5) Contractor duties
6) Manage H&S (inductions, site welfare, site rules)