H&S Test 2 Flashcards
CDM Regulation 2 defines “construction work” as…
The carrying out of any building, civil engineering or engineering construction work (with list of inclusions)
Two specific phases of projects under CDM are…
1) Pre-construction phase
2) Construction phase
Four key CDM documents are…
1) F10 Document
2) PCI - Pre Construction Info
3) CPP - Construction Phase Plan
4) H&SF - Health & Safety File
Three key parties to a project under CDM…
1) Client
2) Principal designer
3) Principal contractor
True or false;
There can be only one entity to each key duty holder position i.e. client, PD, PC)
True;
While there may be more than one client, designer and or contractor one entity should be nominated to hold each key position for the purposes of CDM
Filing of F10 document is the responsibility of…
The client (or their appointed specialist to carry out on their behalf)
Compiling PCI is carried out by…
Combination of client and principal designer
CPP is produced by
Principal contractor
H&SF is compiled by….
Either the principal designer or principal contractor
F10 document is used to…
Inform HSE of any projects which are over 500 person days in duration or have a duration of over 30 days with over 20 operatives
Examples of info within the PCI are (5);
1) Planning and design info
2) Client requirements
3) Survey results
4) Details of any existing hazards
5) Details of any hazards within the design
The CPP contains items such as (4) and is used to manage the site safely
1) H&S site management policies and procedures
2) Site rules
3) Site controls
4) Site welfare details
The H&SF is issued to the ____________ upon completion of the works and provides details such as (4)
Client / end user
1) O&M info
2) Details of residual hazards
3) H&S info relevant to future works
True or false;
One entity can occupy more than one key duty holder position;
True;
The principal designer and principal contractor can be the same entity
Key CDM acronym;
SKE
Stands for…
Skills, knowledge and experience