Group 2 Flashcards
What is BREEAM?
Building Research Establishment Environmental Assessment Method:
- It is a sustainability assessment method
- It sets standards for the environmental performance of buildings through design, specification, construction and operation phases
What are the three pillars of sustainability?
- Social
- Economic
- Environmental
What are the different levels of BREEAM?
- Unclassified Less than 30%
- Pass - 30%
- Good - 45%
- Very good - 55%
- Excellent - 70%
- Outstanding - 85%
What are PV Panels?
Photovoltaic Panels are used to produce electricity directly from sunlight.
What is SUDS?
Sustainable Urban Drainage Systems:
- Designed to both manage the flood and pollution risks resulting from urban runoff and to contribute where possible to environmental enhancement and place making.
What is a blue roof?
A blue roof is designed to attenuate storm water within a void. Which sits directly above the waterproofing layer and beneath a surface finish such as a vegetated green roof or hard landscaping.
- Designed to allow controlled attenuation of rain fall during heavy and storm events.
What is a green roof?
Roofs that are partially or completely covered with plants or vegetation.
How does life cycle costing work?
Process in which the project team assesses the cost of a building, building materials, or piece of equipment throughout its entire useful life.
What is lean construction?
Name some types of foundations?
- Strip Foundation
- Pad Foundation
- Raft Foundation
Name some types of piles?
- Contiguous Piling
- Secant Piling
- CFA Piles
What is Contiguous Piling?
A series of adjacent piles constructed to form an earth retaining structure as a cantilever or propped cantilever wall.
Consist of a row of successive unconnected cast-in-situ concrete piles constructed with small gaps between adjacent piles.
What is Secant Piling?
- Formed by constructing reinforced concrete piles that interlock
- Often used as a cost-effective solution when short-term water retention is required.
- Are reinforced with either steel rebar or steel beams
- Typically, primary (female) piles are cast in situ, leaving space in between them. This is followed by secondary (male) piles being cut into the primary piles to for a continuous wall, generally with a typical interlock of around 150mm.
Advantages of secant piling?
- Provide greater stiffness compared to sheet piles
- Can be installed with difficult ground conditions
- Less noisy than other methods of piling
Disadvantages of secant piling?
- Vertical tolerances difficult to achieve for deep piles
- Higher cost than sheet piles
- Total Waterproofing is difficult to achieve in joints