Group 1 Flashcards

1
Q

What are extensions of time?

A

Extensions of time adjust the completion date and relieves the contractors liability to pay liquidated damages for the period of the extension.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are liquidated damages?

A

A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What must be in place before LDs can be deducted?

A
  • A non-completion certificate

- A withholding notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What if the employer actually suffered no loss or damage?

A

The damages can still be deducted at the value stated in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the benefits of being able to grant an extension of time?

A
  • it relieves the contractors liability for liquidated damages for a delay that they did not cause
  • it enables another completion date to be set, which maintains the employers ability to deduct liquidates damages if another delay occurs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens when ‘time is at large’?

A
  • There is no set completion date
  • the contractor only has the obligation to complete the works in a ‘reasonable time’
  • liquidated damages cannot be claimed as there is no date to take them from
  • the employer would have to try and prove that the contractor had not completed the works in a reasonable time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are relevant events in a JCT form of contract?

A

They are events that entitle the contractor to an extension of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the relevant events?

A

There are 13 relevant events set out in JCT forms including:

  • variations
  • instructions
  • execution of an approximate quantity that is not reasonable accurate forecast
  • deferment of possession of the site
  • suspension by the contractor for non-payment
  • the carrying out of work by statutory authorities
  • impediment, prevention or default by the employer
  • loss or damages occasioned by the Specified Perils
  • exceptionally adverse weather conditions
  • strike or lock out
  • Civil commotion or terrorism
  • the exercise of any statutory power after the base date by the UK govt
  • force majeure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the main elements you would include within an interim valuation?

A
  • Preliminaries
  • measured works
  • variations
  • materials on site
  • materials off site
  • loss and expense
  • retention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What needs to be in place for you to include payments for materials on site?

A
  • the materials should be for the works
  • they should be adequately protected
  • delivered to programme
  • in a reasonable quantity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What needs to be in place for you to include payments for materials off site?

A
  • proof that ownership will transfer to the employer upon payment (vesting certificate)
  • Insurance until materials arrive at site
  • materials are clearly labelled as for the site and set apart from other materials
  • a materials off site bond has been provided if required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a retention of title clause?

A
  • Where the sun-contractor or supplier retains ownership of materials until they are paid for them by the contractor
  • this highlights the importance of vesting certificates as the employer may pay for materials that are not owned by the contractor
  • this legal principle can lead to disputes in the event of insolvency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you evaluate interim valuations?

A
  • go to site and inspect the works to form a view on the percentage of works undertaken
  • check for materials on site and Materials off site
  • value time related and fixed preliminaries items undertaken
  • value any agreed variations and claims
  • the valuation amount is presented as the gross valuation, less previous payment made and retention
  • finally I would send my recommendation to the EA or contract administrator for them to prepare the payment certificate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do stage payments work?

A
  • the stages and their values are set out in the contract particulars
  • the stages are usually related to the completion of significant design items for example completion of substructure or achieving a water tight structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the interim certificate conclusive of?

A
  • Interim certificates are not conclusive
  • they carry no contractual significance to state that the quality of materials or workmanship is satisfactory
  • it is only the final certificate that is conclusive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly