Housing Grants, Construction & Regeneration Act 1996
Local Democracy, Economic development and construction act 2009
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
What is the Housing Grants, Construction and Regeneration Act 1996?
A
Introduced to help payments and dispute resolutions
Interim / Periodic payment if programme is larger than 45 days
Right to know amount of payment / what is being withheld
Right to suspend works for non-payment
Right to adjudication INTERIM PAYMENTS, AMOUNT DUE, SUSPENSION, ADJUDICATION
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
What is the Local Democracy, Economic Development and Construction Act 2009?
A
Introduced to firm loopholes in the HGCR 1996
Contracts do not need to be in writing, verbal contracts can adjudicate
Pay when certified clauses ineffective, MC cannot withhold payment to SC until they are paid
Default payment notice introduced - if payer doesn’t issue notice payee can issue and this amount then becomes due VERBAL AGREEMENTS, PAY WHEN CERTIFIED, DEFAULT PAYMENT NOTICE