Glossary B 02 Flashcards
Earned Value Management (EVM)
is a project management technique that combines measurements of project scope, schedule, and cost in a single, integrated system.
Earned Value Management (EVM) B
EVM is used to assess project performance and progress by comparing the planned progress and costs to the actuals, enabling project managers to understand if the project is on track or facing any cost or schedule variances.
01 . Core EVM Metrics
01 . Planned Value (PV)
02 . Earned Value (EV)
03. Actual Cost (AC)
- Planned Value (PV)
The budgeted amount for the work scheduled to be completed by a given date. It shows how much work should be done at a specific point in time.
- Earned Value (EV)
The budgeted amount for the actual work completed by a given date. It represents the value of the work actually performed.
- Actual Cost (AC)
The actual cost incurred for the work completed by a given date.
02 . Key EVM Performance Indicators
01 . Cost Variance (CV)
02 . Schedule Variance (SV)
- Cost Variance (CV)
CV=EV−AC This measures cost performance by showing if the project is under or over budget.
If CV > 0: The project is under budget; If CV < 0: The project is over budget.
- Schedule Variance (SV)
SV=EV−PV This measures schedule performance, indicating if the project is ahead or behind schedule. If SV > 0: The project is ahead of schedule; If SV < 0: The project is behind schedule.
03 . Performance Index
01 . Cost Performance Index (CPI)
02 . Schedule Performance Index (SPI)
- Cost Performance Index (CPI)
CPI= EV / AC This index shows the cost efficiency of the work completed.
If CPI > 1: The project is cost-efficient; If CPI < 1: The project is costing more than planned.
- Schedule Performance Index (SPI)
SPI= EV / PV This index shows the schedule efficiency of the work completed.
If SPI > 1: The project is ahead of schedule; If SPI < 1: The project is behind schedule.
04 . Forecasting Metrics
01 . Estimate at Completion (EAC)
02 . Estimate to Complete (ETC)
03 . Variance at Completion (VAC)
- Estimate at Completion (EAC)
Estimate at Completion (EAC): A forecast of the total cost at project completion based on current performance.
Formula: EAC= BAC / CPI , where BAC is the Budget at Completion.
- Estimate to Complete (ETC)
The expected cost to finish all remaining project work.