Glossary B 02 Flashcards

1
Q

Earned Value Management (EVM)

A

is a project management technique that combines measurements of project scope, schedule, and cost in a single, integrated system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value Management (EVM) B

A

EVM is used to assess project performance and progress by comparing the planned progress and costs to the actuals, enabling project managers to understand if the project is on track or facing any cost or schedule variances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

01 . Core EVM Metrics

A

01 . Planned Value (PV)
02 . Earned Value (EV)
03. Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • Planned Value (PV)
A

The budgeted amount for the work scheduled to be completed by a given date. It shows how much work should be done at a specific point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • Earned Value (EV)
A

The budgeted amount for the actual work completed by a given date. It represents the value of the work actually performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • Actual Cost (AC)
A

The actual cost incurred for the work completed by a given date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

02 . Key EVM Performance Indicators

A

01 . Cost Variance (CV)
02 . Schedule Variance (SV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  • Cost Variance (CV)
A

CV=EV−AC This measures cost performance by showing if the project is under or over budget.
If CV > 0: The project is under budget; If CV < 0: The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • Schedule Variance (SV)
A

SV=EV−PV This measures schedule performance, indicating if the project is ahead or behind schedule. If SV > 0: The project is ahead of schedule; If SV < 0: The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

03 . Performance Index

A

01 . Cost Performance Index (CPI)
02 . Schedule Performance Index (SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • Cost Performance Index (CPI)
A

CPI= EV / AC This index shows the cost efficiency of the work completed.
If CPI > 1: The project is cost-efficient; If CPI < 1: The project is costing more than planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  • Schedule Performance Index (SPI)
A

SPI= EV / PV This index shows the schedule efficiency of the work completed.
If SPI > 1: The project is ahead of schedule; If SPI < 1: The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

04 . Forecasting Metrics

A

01 . Estimate at Completion (EAC)
02 . Estimate to Complete (ETC)
03 . Variance at Completion (VAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • Estimate at Completion (EAC)
A

Estimate at Completion (EAC): A forecast of the total cost at project completion based on current performance.
Formula: EAC= BAC​ / CPI , where BAC is the Budget at Completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • Estimate to Complete (ETC)
A

The expected cost to finish all remaining project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • Variance at Completion (VAC)
A

Shows the expected budget surplus or deficit at project completion.
Formula: VAC=BAC−EAC

17
Q

Benefits of EVM

A

Improves Visibility: EVM provides insight into both current performance and future project trends.
Identifies Risks Early: Variances in cost and schedule are visible early, allowing corrective actions.
Quantifies Project Health: The metrics make it possible to quantify progress, budget status, and time performance.
Enables Better Decision-Making: Project managers and stakeholders can make informed decisions to optimize resources, adjust schedules, or control costs.

18
Q

Challenges of EVM

A

Requires Accurate Baselines: EVM relies heavily on accurate baselines for cost and schedule, making it difficult if initial estimates are inaccurate.

Complexity in Implementation: Tracking and analyzing EVM metrics can be complex, especially in large or dynamic projects.

Focus on Cost Over Quality: EVM highlights cost and schedule, but quality and resource availability may need separate metrics.

19
Q

To-Complete Performance Index (TCPI)

A

is an Earned Value Management (EVM) metric that helps determine the level of cost performance required to complete a project within a specified budget.

20
Q

To-Complete Performance Index (TCPI)

A

Essentially, it shows how efficiently remaining funds need to be used to meet a specific goal, especially when a project is off track or when budget constraints are tight.