Q

What’s are the stages in the RIBA Plan of work 2020

A
Stage 0 - Strategic Definition 
Stage 1 - Preparation and Briefing 
Stage 2 - Concept Design
Stage 3 - Spatial Co-ordinated 
Stage 4 - Technical Design 
Stage 5 - Manufacturing and Construction
Stage 6 - Handover
Stage 7 - Use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the aim of stage 0 in RIBA plan of works

A

Working out the best means of meeting client requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the aim of stage 1 in RIBA plan of works

A

Project brief approved and confirmed it can be accommodated on site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the aim of stage 2 in RIBA plan of works

A

Architectural concept approved by client and aligned to project brief

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the aim of stage 3 in RIBA plan of works

A

Architectural and engineering information spatially co-ordinated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the aim of stage 4 in RIBA plan of works

A

All design information required to manufacture and construct project is completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the aim of stage 5 in RIBA plan of works

A

Manufacturing, Construction and Commissioning Completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the aim of stage 6 in RIBA plan of works

A

Building handed over, aftercare initiated and building contract concluded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the aim of stage 7 in RIBA plan of works

A

Building used, operated and manufactured efficiently

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Name 5 of the 15 Building regulations

A

A - Structure
B - Fire Strategy
C - Site preparation and resistance to contamination and moisture
D - Toxic Structures
E - Resistance to sound
F - Ventilation
G - Sanitation, hot water and water efficiency
H - Drainage and waste disposal
J - Combustion appliances and fuel storage
K - Protection from falling, collision and impact
L - Conservation of fuel and power
M - Access to and use of the building
P - Electrical Safety
Q - Security in dwelling
R - High speed electronic communication network

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was building regulation N and why was it removed?

A

N was Glazing safety and was subsumed within K in April 2012

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are Building Regulations?

A

Building regulations are a set standard instruments for the design and construction of buildings to ensure the safety and health for people in or about those buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Under JCT is COVID-19 a relevant event or relevant matter?

A

Relevant event under Force Majeure meaning they can claim and EOT but not Additional costs through a Loss & Expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly