the first step to planning a new strength and conditioning facility is
forming a committee of professionals
predesign phase
usually requires 25% of the total project time (6 months). greatest priority is creating a needs analysis or assessment. A feasibility study is conducted to determine costs, facility location, programs of interest.
design phase
may require 10-12% of the total project time (~3 months. Work with the architect to finalize blueprints, include equipment specifications, spacing is designed to be user friendly, facility is designed to provide easy access to all athletes.
construction phase
normally 505 of total project time (about 12 months). deadlines must be set and adhere to.
preoperation phase
also called the start-up phase requires about 15% of total project time (3-4 months) focuses on staffing considerations.