Burner assemblies and all component parts shall be installed according to the ______.
manufacturers instructions and shall be properly and firmly secured in place to maintain correct alignment in normal use.
Linkage for controlling air and gas input rates are designed to ______.
reliably maintain correct air-gas ratio.
When shall combustion control be provided?
for burners with a firing rate of 2,500,000 BTUs per combustion chamber per hour and over
Gas main pressure regulators and gas pressure interlocks. Each burner assembly shall be equipped with a ___(A)___ main gas pressure regulator that will regulate within ___(B)___.
(A) listed
(B) plus or minus 10% of the operating pressure at all firing rates.
Vent lines from main gas pressure regulators shall not be connected into a ___(A)___ with the bleed line from gas operated ___(B)___.
(A) common line
(B) diaphragm valves or from pressure relief valves
vent lines shall be run to the outside using ___(A)___ and shall not be ___(B)___.
(A) shortest practical route
(B) trapped or installed in a manner that restricts air flow
Name 3 things for pilot testing.
1.) pilot burner shall be lighted and adjusted to manufacturers instructions
2.) pilots shall not deposit carbon
3.) when bleed pilots are used the discharge shall be in a fixed position