Formulas Flashcards
PERT Triangular Distribution
Estimated Activity Duration (EAD) = Optimistic + Most Likely + Pessimistic divided by 3
EAD = (O+M+P)/3
PERT Beta Distribution
Estimated Activity Duration (EAD) = Optimistic + (4 x Most Likely) + Pessimistic divided by 6
EAD = (O+4M+P)/6
Standard Deviation (SD) of Activity
Standard Deviation (SD) = Pessimistic - Optimistic divided by 6
SD = (P-O)/6
Variance of an Activity
Variance = Pessimistic - Optimistic divided by 6 squared
[(P - O)/6 ]^2
Range of Activity Duration
Range of an Activity Duration=Estimated Activity Duration (EAD) ± Standard Deviation (SD)
Range = EAD ± SD
Total Float (how long activity can be delayed before affecting end date)
Total Float = Late Start (LS) - Early Start (ES)
TF = LS - ES
OR
Total Float = Late Finish (LF) - Early Finish (EF)
TF = LF-EF
Cost Variance (CV)
Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)
CV = EV-AC
Schedule Variance (SV)
Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)
SV = EV-PV
Cost Performance Index (CPI)
Cost Performance Index (CPI) = Earned Value divided by Actual Cost
CPI = EV/AC
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) = Earned Value (EV) divided by Planned Value (PV)
SPI = EV/PV
Budget at Completion (BAC)
BAC includes contingency reserves for activities and defines how much money will be spent during project in total
Estimate to Complete (ETC)
Estimate to Complete (ETC) is the estimation of the remaining work
ETC = Estimate at Completion (EAC) - Actual Cost (AC) ETC = EAC-AC
Estimate at Completion (EAC)
@budgeted rate:
Estimate at Completion (EAC) = Actual Cost (AC) + (Budget At Completion (BAC) - Earned Value (EV))
EAC = AC+(BAC-EV)
@same cost performance:
EAC = BAC divided by Cost Performance Index (CPI)
EAC = BAC/CPI
EAC = BAC/(EV/AC)
@rate that considers cost and schedule
EAC = AC + [(BAC-EV)/CPI x Schedule Performance Index (SPI)]
EAC = AC + [(BAC-EV)/(CPISPI)]
EAC = AC + [(BAC-EV)/((EV/AC)(EV/PV))]
Variance at Completion (VAC)
Variance at Completion (VAC) = Budget at Completion (BAC) - Estimate at Completion (EAC)
VAC = BAC-EAC
To-Complete Performance Index (TCPI)
without EAC Value:
To-Complete Performance Index (TCPI) = Budget at Completion (BAC) - Earned Value (EV) divided by BAC - Actual Cost (AC)
TCPI = (BAC-EV)/(BAC-AC)
With EAC Value:
TCPI = BAC-EV divided by Estimate at Completion (EAC) - AC
TCPI = BAC-EV/EAC-AC