Formulas Flashcards
Present Value (Integration Management)
FV / ( 1 + i )nth
Expected Activity Duration - Triangular (Time Management and Cost Management)
O + M + P / 3
Expected Activity Duration - Beta/PERT (Time Management and Cost Management)
O + 4M + P / 6
Standard Deviation of an Activity - SD (Time Management and Cost Management)
P - O / 6
Activity Variance (Time Management and Cost Management)
SD 2nd
Range of Activity Duration (Time Management and Cost Management)
EAD +/- SD
Early Finish - EF (Time Management)
ES + Duration - 1
Late Start - LS (Time Management)
LF - Duration + 1
Total Float (Time Management)
LS - ES, or LF - EF
Critical Path (Time Management)
Sum of longest duration path
Cost Variance - CV (Cost Management)
EV - AC
Schedule Variance - SV (Cost Management)
EV - PV
Cost Performance Index - CPI (Cost Management)
EV / AC
Schedule Performance Index - SPI (Cost Management)
EV / PV
Estimate At Completion (EAC), using the most accurate method (Cost Management)
AC + Bottom-up ETC