Earned Value Management Meanings Flashcards
CV
Cost Variance (Negative is bad, Positive is good)
SV
Schedule Variance (Negative is bad, Positive is good)
CPI
Cost Performance Index (Under 1 is bad, Over 1 is good)
SPI
Schedule Performance Index (Under 1 is bad, Over 1 is good)
EAC
Estimate at Completion
ETC
Estimate to Completion (Value of work remaining)
VAC
Variance at Completion (Negative is bad, Positive is good)
TCPI
To Complete Performance Index
PV
Planned Value (Budgeted value of work planned to be done)
EV
Earned Value (Budgeted value of work completed)
AC
Actual Costs (Actual total costs of work completed)
BAC
Budget at Completion (Cost Baseline)
EAC
Expected at Completion (Expected total costs - Forecast)
ETC
Estimate to Complete (Expected remaining cost; now until end)
VAC
Variance at Completion (Expected variance over/under budget)