Formulas Flashcards

1
Q

What is Net Present Value (NPV) used for?

A

NPV is used for project selection. Always select the project with the highest NPV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is Net Present Value (NPV) calculated?

A

NPV = Year 0 Initial Investment + [Cash Flow 1 / (1 + Discount Rate) ^1] + [Cash Flow 2 / (1 + Discount Rate) ^2] + [Cash Flow 3 / (1 + Discount Rate) ^3] …

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the formula for PERT (Program Evaluation and Review Technique) using Triangular Distribution?

A

PERT = (Optimistic + Most Likely + Pessimistic) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for PERT using Beta Distribution?

A

PERT = (Optimistic + (4 × Most Likely) + Pessimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do you calculate Standard Deviation in PERT?

A

Standard Deviation (SD) = (Pessimistic - Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for Risk Rating in qualitative risk analysis?

A

Risk Rating = Probability × Impact (Expressed as a percentage or decimal)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is Expected Monetary Value (EMV) calculated?

A

EMV = Probability × Impact (Expressed as a dollar amount)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you calculate the number of communication channels?

A

Communication Channels = n(n-1)/2, where n = number of team members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How is the Make or Buy Analysis equation structured?

A

Cost to Make = Cost to Buy (Lease). Solve for X (breakeven point): Initial Cost + (Daily Cost × X) = Cost to Lease + (Daily Lease Cost × X).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the formula for calculating Float?

A

Float = Late Start - Early Start, or Float = Late Finish - Early Finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How is Planned Value (PV) calculated?

A

PV = Budget at Completion (BAC) × Percent of Time Passed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How is Earned Value (EV) calculated?

A

EV = Budget at Completion (BAC) × Percent of Work Completed.

25
Q

What is Actual Cost (AC)?

A

The amount of money spent on approved project work to date. AC may also be given as AC = BAC - Money Left.

27
Q

How is Schedule Variance (SV) calculated?

A

SV = Earned Value (EV) - Planned Value (PV).

29
Q

How is Schedule Performance Index (SPI) calculated?

A

SPI = Earned Value (EV) / Planned Value (PV).

31
Q

How is Cost Variance (CV) calculated?

A

CV = Earned Value (EV) - Actual Cost (AC).

33
Q

How is Cost Performance Index (CPI) calculated?

A

CPI = Earned Value (EV) / Actual Cost (AC).

35
Q

What are the four different formulas for Estimate at Completion (EAC)?

37
Q

EAC = BAC / CPI (Assumes same rate of spending continues)

39
Q

EAC = AC + (BAC - EV) or EAC = BAC - CV (Assumes one-time deviation)

41
Q

EAC = AC + [(BAC - EV) / (CPI × SPI)] (For poor cost performance and firm deadline)

43
Q

EAC = AC + Estimate to Complete (ETC) (For flawed original budget)

45
Q

How is Estimate to Complete (ETC) calculated?

A

ETC = Estimate at Completion (EAC) - Actual Cost (AC).

47
Q

What is the formula for To Complete Performance Index (TCPI)?

49
Q

TCPI = (BAC - EV) / (BAC - AC) (if using original budget)

51
Q

TCPI = (BAC - EV) / (EAC - AC) (if budget is rebaselined)

53
Q

How is Variance at Completion (VAC) calculated?

A

VAC = Budget at Completion (BAC) - Estimate at Completion (EAC).

55
Q

What is the formula for Burn Rate?

A

Burn Rate = 1 / Cost Performance Index (CPI). A burn rate <1 means under budget, while >1 means over budget.