Formulas Flashcards
What is Net Present Value (NPV) used for?
NPV is used for project selection. Always select the project with the highest NPV.
How is Net Present Value (NPV) calculated?
NPV = Year 0 Initial Investment + [Cash Flow 1 / (1 + Discount Rate) ^1] + [Cash Flow 2 / (1 + Discount Rate) ^2] + [Cash Flow 3 / (1 + Discount Rate) ^3] …
What is the formula for PERT (Program Evaluation and Review Technique) using Triangular Distribution?
PERT = (Optimistic + Most Likely + Pessimistic) / 3
What is the formula for PERT using Beta Distribution?
PERT = (Optimistic + (4 × Most Likely) + Pessimistic) / 6
How do you calculate Standard Deviation in PERT?
Standard Deviation (SD) = (Pessimistic - Optimistic) / 6
What is the formula for Risk Rating in qualitative risk analysis?
Risk Rating = Probability × Impact (Expressed as a percentage or decimal)
How is Expected Monetary Value (EMV) calculated?
EMV = Probability × Impact (Expressed as a dollar amount)
How do you calculate the number of communication channels?
Communication Channels = n(n-1)/2, where n = number of team members.
How is the Make or Buy Analysis equation structured?
Cost to Make = Cost to Buy (Lease). Solve for X (breakeven point): Initial Cost + (Daily Cost × X) = Cost to Lease + (Daily Lease Cost × X).
What is the formula for calculating Float?
Float = Late Start - Early Start, or Float = Late Finish - Early Finish.
How is Planned Value (PV) calculated?
PV = Budget at Completion (BAC) × Percent of Time Passed.
How is Earned Value (EV) calculated?
EV = Budget at Completion (BAC) × Percent of Work Completed.
What is Actual Cost (AC)?
The amount of money spent on approved project work to date. AC may also be given as AC = BAC - Money Left.
How is Schedule Variance (SV) calculated?
SV = Earned Value (EV) - Planned Value (PV).
How is Schedule Performance Index (SPI) calculated?
SPI = Earned Value (EV) / Planned Value (PV).
How is Cost Variance (CV) calculated?
CV = Earned Value (EV) - Actual Cost (AC).
How is Cost Performance Index (CPI) calculated?
CPI = Earned Value (EV) / Actual Cost (AC).
What are the four different formulas for Estimate at Completion (EAC)?
EAC = BAC / CPI (Assumes same rate of spending continues)
EAC = AC + (BAC - EV) or EAC = BAC - CV (Assumes one-time deviation)
EAC = AC + [(BAC - EV) / (CPI × SPI)] (For poor cost performance and firm deadline)
EAC = AC + Estimate to Complete (ETC) (For flawed original budget)
How is Estimate to Complete (ETC) calculated?
ETC = Estimate at Completion (EAC) - Actual Cost (AC).
What is the formula for To Complete Performance Index (TCPI)?
TCPI = (BAC - EV) / (BAC - AC) (if using original budget)
TCPI = (BAC - EV) / (EAC - AC) (if budget is rebaselined)
How is Variance at Completion (VAC) calculated?
VAC = Budget at Completion (BAC) - Estimate at Completion (EAC).
What is the formula for Burn Rate?
Burn Rate = 1 / Cost Performance Index (CPI). A burn rate <1 means under budget, while >1 means over budget.