Day 1 Flashcards

1
Q

Project; A temporary endeavor undertaken to create a unique product

A

service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Project Management; The application of knowledge

A

skills

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Stakeholder; An individual

A

group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Scope; The sum of products

A

services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Work Breakdown Structure (WBS);

A

A hierarchical decomposition of the total scope of work to accomplish project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk Management; The process of identifying

A

analyzing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical Path; The longest sequence of activities that determines the shortest possible duration for a project.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Earned Value (EV); A measure of work performed expressed in terms of the budget authorized for that work.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost Performance Index (CPI); A measure of cost efficiency calculated as Earned Value (EV) divided by Actual Cost (AC).

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Schedule Performance Index (SPI); A measure of schedule efficiency calculated as Earned Value (EV) divided by Planned Value (PV).

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Agile; A mindset and methodology focused on iterative development

A

collaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Scrum; An Agile framework with predefined roles

A

events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Sprint; A fixed time period (e.g.

A

2 weeks) in which a Scrum team works to complete a set amount of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Kanban; A visualization tool to manage workflow by making bottlenecks and work quantities visible.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Monte Carlo Analysis; A statistical technique used to assess project risks and forecast probable outcomes.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Change Control; The process of identifying

A

documenting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Milestone; A significant point in a project schedule marking the completion of a phase or key event.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Risk Register; A document that captures all identified risks and their response strategies.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Burndown Chart; A graphical representation of work remaining versus time remaining in a timebox.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Daily Scrum; A short daily meeting for Agile teams to review progress and plan work for the day.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Definition of Done (DoD); A shared understanding of the criteria required to declare a deliverable as complete.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Story Point; A unit of measure used in Agile to estimate work effort relative to other tasks.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Net Present Value (NPV); A financial metric that calculates the value of future cash flows in today’s terms.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Return on Investment (ROI); A financial metric used to measure the profitability of a project investment.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Opportunity Cost; The potential return that will not be realized when one project is selected over another.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Change Management; A structured approach for transitioning individuals

A

groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Lessons Learned; Documented knowledge gained during a project that can be used to improve future projects.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

PMO (Project Management Office); An organizational structure that standardizes project-related governance and facilitates resource sharing.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Project Charter; A document that formally authorizes a project and provides a high-level overview of objectives and scope.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Business Case; A justification for a project

A

including cost-benefit analysis and expected value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Adaptive Planning; High-level planning at the beginning

A

with detailed planning as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Backlog; An ordered list of requirements or tasks in Agile development.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Cost Baseline; The approved version of cost estimates plus contingency reserves

A

used for tracking project expenses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Lead Time; The total time taken from the initiation of a work item to its completion.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Collocated Team; A project team that works in the same physical location to enhance collaboration.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Contingency Plan; A predefined action plan for responding to identified project risks.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Total Float; The amount of time an activity can be delayed without delaying the overall project completion.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Affinity Estimate; A technique for high-level estimation by grouping work items based on size and making relative estimations.

39
Q

Backward Pass; A technique in critical path method for calculating late start and late finish dates.

40
Q

Benefit-Cost Ratio (BCR); A financial metric comparing proposed costs and expected benefits; a BCR greater than 1.0 is favorable.

41
Q

Behavior-Driven Development (BDD); An Agile methodology that focuses on expected user behavior in test cases.

42
Q

Cost of Quality (COQ); A method for determining resource allocation to prevent or rectify defects.

43
Q

Estimate at Completion (EAC); The projected total cost of completing all work.

44
Q

Artifacts; Tangible by-products of a project that provide transparency

A

such as a product backlog or design documents.

45
Q

Audit; A structured process to assess and verify compliance with organizational and project policies.

46
Q

Governance Board; A project oversight body responsible for reviewing key deliverables and guiding project decisions.

47
Q

Governance Checkpoints; Phase gates or iteration reviews used to ensure compliance and alignment with project objectives.

48
Q

Project Phases; Sequential steps within a project

A

often including initiation

49
Q

Process Improvement; Continuous evaluation and enhancement of project processes to maximize efficiency and effectiveness.

50
Q

Lessons Learned Register; A collection of knowledge gained from past projects to inform future project decisions.

51
Q

ECO (Exam Content Outline); The framework defining the PMP exam domains and key knowledge areas.

52
Q

What is the purpose of definitions in a text?

A

To clarify the meaning of terms and concepts.

53
Q

True or False: All definitions are included in the answer side of a text.

54
Q

Fill in the blank: Definitions that are not included may lead to ______ in understanding.

55
Q

What is a potential consequence of missing definitions?

A

Misinterpretation of key concepts.

56
Q

Multiple Choice: What should be done if definitions are missing from a text? A) Ignore them B) Fix them C) Add more definitions D) Rewrite the entire text

A

B) Fix them

57
Q

What is a common reason for definitions being omitted?

A

Oversight during the editing process.

58
Q

True or False: Definitions should only be included at the beginning of a text.

59
Q

What is one method to ensure all definitions are included?

A

Conduct a thorough review of the text.

60
Q

Fill in the blank: A well-defined term enhances ______ in communication.

61
Q

What role do definitions play in professional certifications?

A

They provide essential knowledge for understanding key concepts.

62
Q

Multiple Choice: Which of the following is NOT a type of definition? A) Operational B) Descriptive C) Ambiguous D) Stipulative

A

C) Ambiguous

63
Q

True or False: Definitions can be subjective and vary between different fields.

64
Q

What action should be taken if a definition is unclear?

A

Seek clarification or revise the definition.

65
Q

Fill in the blank: Definitions should be ______ and concise.

66
Q

What is the benefit of including examples with definitions?

A

They help illustrate the meaning more effectively.

67
Q

Multiple Choice: Which term refers to a definition that specifies the meaning of a term for the purposes of a particular discussion? A) Descriptive B) Stipulative C) Lexical D) Theoretical

A

B) Stipulative

68
Q

True or False: Definitions should remain static and never change.

69
Q

What is an essential characteristic of a good definition?

A

It should be precise and unambiguous.

70
Q

Fill in the blank: The inclusion of definitions can aid in ______ understanding.

A

comprehending

71
Q

What should you do if you notice a missing definition during review?

A

Add the definition and ensure it’s accurate.

72
Q

Multiple Choice: In what section of a text are definitions typically found? A) Introduction B) Conclusion C) Appendix D) Glossary

A

D) Glossary

73
Q

True or False: Definitions are only necessary in technical writing.

74
Q

What is a lexicon?

A

A collection of words and their meanings in a specific language.

75
Q

Fill in the blank: A missing definition can lead to a ______ in the reader’s understanding.

76
Q

What is one strategy to prevent missing definitions in a text?

A

Create a checklist of required terms and definitions.

77
Q

Multiple Choice: Which of the following is a type of definition that describes how a term is commonly used? A) Operational B) Lexical C) Theoretical D) Stipulative

A

B) Lexical

78
Q

True or False: Definitions should be tailored to the audience’s knowledge level.

79
Q

What is a synonym for the term ‘definition’?

A

Explanation

80
Q

Fill in the blank: Definitions help to establish a common ______ among readers.

A

understanding

81
Q

What is the impact of using jargon without definitions?

A

It can alienate readers who are unfamiliar with the terms.

82
Q

Multiple Choice: What is the purpose of a glossary? A) To summarize the text B) To provide definitions C) To list references D) To outline the main points

A

B) To provide definitions

83
Q

True or False: A well-defined term can improve the quality of a text.

84
Q

What is the role of context in understanding definitions?

A

Context helps clarify the meaning of terms based on their usage.

85
Q

Fill in the blank: The process of defining terms is known as ______.

A

definition

86
Q

What should be the priority when reviewing a text for missing definitions?

A

Identify and add all essential definitions.

87
Q

Multiple Choice: Which of the following best describes a ‘descriptive definition’? A) It explains how a term is used in practice B) It assigns a new meaning C) It provides a strict meaning D) It is vague

A

A) It explains how a term is used in practice

88
Q

True or False: Definitions can vary in length and complexity.

89
Q

What is an operational definition?

A

A definition that specifies the procedures or actions required to measure a concept.

90
Q

Fill in the blank: A clear definition can facilitate ______ in discussions.

A

communication

91
Q

What should be avoided when writing definitions?

A

Using overly complex language or jargon.

92
Q

Multiple Choice: Which of the following is an example of a clear definition? A) ‘Bad’ B) ‘A bad experience is one that is unpleasant or negative.’ C) ‘It depends’ D) ‘You know what I mean’

A

B) ‘A bad experience is one that is unpleasant or negative.’

93
Q

True or False: Definitions should be reviewed regularly to ensure accuracy.

94
Q

What is the main goal of including definitions in a text?

A

To enhance understanding and communication.